Discussion Forum : Building Construction - Section 1 (Q.No. 47)
47.
The form work from the underside of slabs, can be removed only after
1 day
4 days
7 days
14 days.
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
11 comments Page 2 of 2.

Zahid said:   1 decade ago
7 days for length upto 3.5m and 14 days for length more than 3.5m.