25.
Fixed charges for a chemical plant does not include the
interest on borrowed money.
rent of land and buildings.
property tax, insurance and depreciation.
repair and maintenance charges.
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
1 comments Page 1 of 1.

Kirub said:   2 years ago
The Fixed charges include:

-> Depreciation
-> Rent
-> Insurance
-> Local taxes
But repair and maintenance are under direct production cost.
(2)