Aptitude - Time and Work - Discussion

Discussion Forum : Time and Work - General Questions (Q.No. 9)
9.
A does 80% of a work in 20 days. He then calls in B and they together finish the remaining work in 3 days. How long B alone would take to do the whole work?
23 days
37 days
371/2
40 days
Answer: Option
Explanation:

Whole work is done by A in ( 20 x 5 ) = 25 days.
4

Now, ( 1 - 4 ) i.e., 1 work is done by A and B in 3 days.
5 5

Whole work will be done by A and B in (3 x 5) = 15 days.

A's 1 day's work = 1 , (A + B)'s 1 day's work = 1 .
25 15

Therefore B's 1 day's work = ( 1 - 1 ) = 4 = 2 .
15 25 150 75

So, B alone would do the work in 75 = 37 1 days.
2 2

Discussion:
165 comments Page 9 of 17.

Jyoti said:   9 years ago
A does 80% work means 80÷100 =4/5 work in 20 days.
So, A's 1 day work = 4/5 * 1/20 = 1/25 work in 1day.
Now, It is said that A+B can do a piece of work in 3 days.
Therefore remaining work =1 - 4/5 = 1/5.
So, A+B's 1day work = 1/5 * 1/3 = 1/15.
Now work done by B in 1 day = 1/15-1/25 = 2/75.
Therefore B can do whole work in 75/2.

Hope it is clear to you!

Rahul Berry said:   9 years ago
Thank you for your valid explanation @Baskar.

Muna sharma said:   9 years ago
LCM of 15 and 25 is 150? Isn't it 75?

Muna sharma said:   9 years ago
How 80/100 can be 5/4? It should be 4/5.

Nagendran said:   9 years ago
Can anyone explain B's 1 day's work?

Jiya said:   9 years ago
Still, I'm not getting why its 5/4*20? Please explain briefly.

PrasadJadapalli said:   9 years ago
Super explanation @Snehagoud.

PrasadJadapalli said:   9 years ago
Super explanation @Snehagoud.

Satish said:   9 years ago
A - 20 - 80/100.
A - 1 - 80/(100 * 20) = 1/25.

A and B - 3 days = 20/100.
" 1 " = 20/(100 * 3).
= 1/15.
So,
1/15 -1/25 = 75/2.

Sky said:   9 years ago
Well explained, Thank you @Baskar.