Discussion Forum : Time and Work - General Questions (Q.No. 9)
9.
A does 80% of a work in 20 days. He then calls in B and they together finish the remaining work in 3 days. How long B alone would take to do the whole work?
Answer: Option
Explanation:
Whole work is done by A in | ![]() |
20 x | 5 | ![]() |
= 25 days. |
4 |
Now, | ![]() |
1 - | 4 | ![]() |
i.e., | 1 | work is done by A and B in 3 days. |
5 | 5 |
Whole work will be done by A and B in (3 x 5) = 15 days.
A's 1 day's work = | 1 | , (A + B)'s 1 day's work = | 1 | . |
25 | 15 |
![]() |
![]() |
1 | - | 1 | ![]() |
= | 4 | = | 2 | . |
15 | 25 | 150 | 75 |
So, B alone would do the work in | 75 | = 37 | 1 | days. |
2 | 2 |
Discussion:
164 comments Page 9 of 17.
Rahul Berry said:
9 years ago
Thank you for your valid explanation @Baskar.
Muna sharma said:
9 years ago
LCM of 15 and 25 is 150? Isn't it 75?
Muna sharma said:
9 years ago
How 80/100 can be 5/4? It should be 4/5.
Nagendran said:
9 years ago
Can anyone explain B's 1 day's work?
Jiya said:
9 years ago
Still, I'm not getting why its 5/4*20? Please explain briefly.
PrasadJadapalli said:
9 years ago
Super explanation @Snehagoud.
PrasadJadapalli said:
9 years ago
Super explanation @Snehagoud.
Satish said:
9 years ago
A - 20 - 80/100.
A - 1 - 80/(100 * 20) = 1/25.
A and B - 3 days = 20/100.
" 1 " = 20/(100 * 3).
= 1/15.
So,
1/15 -1/25 = 75/2.
A - 1 - 80/(100 * 20) = 1/25.
A and B - 3 days = 20/100.
" 1 " = 20/(100 * 3).
= 1/15.
So,
1/15 -1/25 = 75/2.
Sky said:
9 years ago
Well explained, Thank you @Baskar.
Wilson said:
9 years ago
A's 1 day work = 80% / 20 days
= 80/20
= 4 ( 4% work per day done by 'A' )
Remaining, (100 - 80) 20% work done by 'A' and 'B' in 3 days.
It means 'A' must have done 4% work per day, So, in 3 Days = 4% * 3.
= 4 * 3.
= 12.(12%work done by 'A' out of 20%).
Now, 8% (20-12) work done by 'B' in 3 Days.
Therefore, 'B' Alone can do Work = 100/8 * 3.
= 37 1/2 days.
= 80/20
= 4 ( 4% work per day done by 'A' )
Remaining, (100 - 80) 20% work done by 'A' and 'B' in 3 days.
It means 'A' must have done 4% work per day, So, in 3 Days = 4% * 3.
= 4 * 3.
= 12.(12%work done by 'A' out of 20%).
Now, 8% (20-12) work done by 'B' in 3 Days.
Therefore, 'B' Alone can do Work = 100/8 * 3.
= 37 1/2 days.