9.
A does 80% of a work in 20 days. He then calls in B and they together finish the remaining work in 3 days. How long B alone would take to do the whole work?
23 days
37 days
371/2
40 days
Answer: Option
Explanation:

Whole work is done by A in ( 20 x 5 ) = 25 days.
4

Now, ( 1 - 4 ) i.e., 1 work is done by A and B in 3 days.
5 5

Whole work will be done by A and B in (3 x 5) = 15 days.

A's 1 day's work = 1 , (A + B)'s 1 day's work = 1 .
25 15

Therefore B's 1 day's work = ( 1 - 1 ) = 4 = 2 .
15 25 150 75

So, B alone would do the work in 75 = 37 1 days.
2 2

Discussion:
166 comments Page 4 of 17.

Jay said:   2 decades ago
@shefali..the 15 days is nothing but remaining work probability. 4/5 i.e 80% work is done by A so remaining is 1-(4/5)= 1/5. its same like p+q=1 in probability.
n same like 3*5=15 days
(1)

Balaji said:   2 decades ago
Thank you very much rajendra.
(1)

Shanmug said:   2 decades ago
@Baskar you have done great job. Just carry on.
(1)

Pratswinz said:   2 decades ago
@Bhaskar your explanation was superb. Carry on dude.
(1)

Mathi said:   1 decade ago
A = (1/20) * (80/100) = 1/25
1/A + 1/B =1/3(20/100)
1/B=(1/15) - (1/25) =2/75
(1)

Riyaz said:   1 decade ago
A does 80% of work in 20 days which means he does 4% of work in a day (80/20 =4).

A and b does the remaining 20% work in 3 days which means in this 20 % of work A's contribution will be 4*3=12%.

Work done by b in 3 days = 20-12 = 8%.

Work done by b in 1 day = 8/3= 2.66.

Time taken by B to complete whole work= 100/2.66= 37.59.

We can't get exact answer but this will be time consuming.
(1)

Namrata Gujar said:   5 years ago
A=80%
Remain 100 - 80 = 20%.

A = (1/20) * (80/100) = 1/25.
A+b = (1/3)+(20/100) = 1/15.
A+b.
(1/25) + b = 1/15.
B = 2/75,
B = 75/2,
B = 37(1/2).
(1)

Narayanan said:   2 months ago
A completes 80% of the work in 20 days, which means 80/100=4/5 unit of work are already completed by A.
therefore, remaining work = 1 - 4/5 = 1/5 units is remaining work,
1/5 work is completed by A + B.

Converting fractions into 1 unit of work.
Formula = total days taken by A to finish work x reciprocal of finished work.
So, A = 20 x 5/4 = 25 days.
A+B = 3 x 5/1 = 15 days.

By substituting A in A+B, we get 75/2, which can be written as 37 1/2.
(1)

Snehagoud said:   2 decades ago
A did only 80% of work out of total work in 20 days so
work done by A=80/100=5/4
so total workdone by A=20*5/4

Shefali said:   2 decades ago
How do we get that A & B together can do work in 15 days?


Post your comments here: