Aptitude - Time and Work - Discussion

Discussion Forum : Time and Work - General Questions (Q.No. 9)
9.
A does 80% of a work in 20 days. He then calls in B and they together finish the remaining work in 3 days. How long B alone would take to do the whole work?
23 days
37 days
371/2
40 days
Answer: Option
Explanation:

Whole work is done by A in ( 20 x 5 ) = 25 days.
4

Now, ( 1 - 4 ) i.e., 1 work is done by A and B in 3 days.
5 5

Whole work will be done by A and B in (3 x 5) = 15 days.

A's 1 day's work = 1 , (A + B)'s 1 day's work = 1 .
25 15

Therefore B's 1 day's work = ( 1 - 1 ) = 4 = 2 .
15 25 150 75

So, B alone would do the work in 75 = 37 1 days.
2 2

Discussion:
164 comments Page 13 of 17.

Shanmug said:   1 decade ago
@Baskar you have done great job. Just carry on.
(1)

Manjula said:   1 decade ago
Awesome explanation by @Bhaskar and @Rajendra.

Shivaputra said:   6 years ago
@ Rajendra.

Thanks for the clear explanation.

Rahul Berry said:   9 years ago
Thank you for your valid explanation @Baskar.

Malini said:   1 decade ago
hey pls tell clearly ya its quite confusing

Abu hanif said:   5 years ago
Please, anyone, help me to get it clearly.

Muna sharma said:   9 years ago
How 80/100 can be 5/4? It should be 4/5.

Abica said:   5 years ago
Nice explanation, Thanks @Vikram Sihag.

Umadatla said:   1 decade ago
1/15-1/25 = 2/75.

How you got 5 1/75?

Sathyabama said:   8 years ago
Easy to understand it. Thanks @Wilson.