Aptitude - Time and Work - Discussion
Discussion Forum : Time and Work - General Questions (Q.No. 13)
13.
A and B can together finish a work 30 days. They worked together for 20 days and then B left. After another 20 days, A finished the remaining work. In how many days A alone can finish the work?
Answer: Option
Explanation:
(A + B)'s 20 day's work = | ![]() |
1 | x 20 | ![]() |
= | 2 | . |
30 | 3 |
Remaining work = | ![]() |
1 - | 2 | ![]() |
= | 1 | . |
3 | 3 |
Now, | 1 | work is done by A in 20 days. |
3 |
Therefore, the whole work will be done by A in (20 x 3) = 60 days.
Discussion:
63 comments Page 7 of 7.
Arya said:
8 years ago
A + B = 1/30 its entire work But
A + B work together only for 20 days so...
A + B - A
1/30 - 1/20
LCM is 60.
So, 2 - 3 ÷60.
1/60 = 60 Days.
A + B work together only for 20 days so...
A + B - A
1/30 - 1/20
LCM is 60.
So, 2 - 3 ÷60.
1/60 = 60 Days.
Poorvi said:
8 years ago
Pushpas work 1/10.
Komals work. 1/20 Per day.
So, they work for 5 days.
Their total work should be calculated by 1/10 + 1/20 then -1/5 you'll get the Answer.
Hope it's correct.
Komals work. 1/20 Per day.
So, they work for 5 days.
Their total work should be calculated by 1/10 + 1/20 then -1/5 you'll get the Answer.
Hope it's correct.
Ankush said:
1 decade ago
Now, 1 work is done by A in 20 days. 3 Therefore, the whole work will be done by A in (20 x 3) = 60 days.
Please can anyone explain me this.
Please can anyone explain me this.
Post your comments here:
Quick links
Quantitative Aptitude
Verbal (English)
Reasoning
Programming
Interview
Placement Papers