Discussion Forum : Time and Work - General Questions (Q.No. 13)
13.
A and B can together finish a work 30 days. They worked together for 20 days and then B left. After another 20 days, A finished the remaining work. In how many days A alone can finish the work?
Answer: Option
Explanation:
(A + B)'s 20 day's work = | ![]() |
1 | x 20 | ![]() |
= | 2 | . |
30 | 3 |
Remaining work = | ![]() |
1 - | 2 | ![]() |
= | 1 | . |
3 | 3 |
Now, | 1 | work is done by A in 20 days. |
3 |
Therefore, the whole work will be done by A in (20 x 3) = 60 days.
Discussion:
63 comments Page 4 of 7.
Poorvi said:
8 years ago
Good explanations. Thank you all.
Poorvi said:
8 years ago
Pushpas work 1/10.
Komals work. 1/20 Per day.
So, they work for 5 days.
Their total work should be calculated by 1/10 + 1/20 then -1/5 you'll get the Answer.
Hope it's correct.
Komals work. 1/20 Per day.
So, they work for 5 days.
Their total work should be calculated by 1/10 + 1/20 then -1/5 you'll get the Answer.
Hope it's correct.
Pooja bhardwaj said:
8 years ago
Thank you for the best and easy explanation @Kaaly and @Senchu Thomas.
Rohit said:
8 years ago
In how many days B will complete the same work?
Foram Rana said:
8 years ago
Nice explanation @Harish.
E ABHILASH GOWD said:
8 years ago
A+B =30 DAYS.
B LEFT 20 DAYS.
A FINSH WORK IN 20 DAYS.
1-1/20 =19/20.
1/30-19/20 =1/60.
60 DAYS.
B LEFT 20 DAYS.
A FINSH WORK IN 20 DAYS.
1-1/20 =19/20.
1/30-19/20 =1/60.
60 DAYS.
PANKAJ PARIHAR said:
8 years ago
What is the total time taken by B? Please answer it.
Sanjana said:
8 years ago
To make the last step easy we can understand it as follows:
1/3work can be done in 20 days.
So, 1 wor will be don win 20 * 3 60 days (try using direct proportion)
1/3work can be done in 20 days.
So, 1 wor will be don win 20 * 3 60 days (try using direct proportion)
Raju said:
8 years ago
A, B, and C working togather can finish cerain piece of work in 40 days. If A and B work together then take 1/3 less time than that of C takes alone. If A andBC work together than they take 1/4 less time than that B takes alone. In how many days B and C working together will finish the work? Can anyone solve this?
Harsimran kaur said:
7 years ago
@Pankaj.
Total time taken by B is 60 days.
Total time taken by B is 60 days.
Post your comments here: