Discussion Forum : Time and Work - General Questions (Q.No. 22)
22.
A and B can complete a work in 15 days and 10 days respectively. They started doing the work together but after 2 days B had to leave and A alone completed the remaining work. The whole work was completed in :
8 days
10 days
12 days
15 days
Answer: Option
Explanation:

(A + B)'s 1 day's work = ( 1 + 1 ) = 1 .
15 10 6

Work done by A and B in 2 days = ( 1 x 2 ) = 1 .
6 3

Remaining work = ( 1 - 1 ) = 2 .
3 3

Now, 1 work is done by A in 1 day.
15

Therefore 2 work will be done by a in ( 15 x 2 ) = 10 days.
3 3

Hence, the total time taken = (10 + 2) = 12 days.

Discussion:
40 comments Page 2 of 4.

Deepak kumar said:   7 years ago
A=15.
B=10.
Total work 30.
One day A Work 2.
One day B work 3.
So 2 days together work 5*2=10.
So remaining work 30-10 =20.
20/2= 10.
10+2= 12 days answer.
(1)

Banodai said:   8 years ago
This problem as it is 11th problem.

B did work 2 days out of 10 days = 2/10 = 1/5.
Remaining work = 1-1/5 = 4/5.
A did 1/15 th work in 1 day.
A did 4/5 th work in ? days.
Cross multiply,

? days = 4/5* 15= 12 days.

Pushpendra said:   8 years ago
I think your method was correct & easy. Thanks @Masud.

Bharathi said:   8 years ago
The work done 6 * 2 = 12 days.

Sunil said:   9 years ago
Why we have to add 2 in the last?

Masud said:   9 years ago
Work per day:

A = 1/15.
B = 1/10.

A work T day = T/15.
B work 2 day = 2/10,

(T/15 + 2/10) = 1.
2T + 6 = 30,
T = 12.

Divya said:   9 years ago
How 1/6 came?

Rushil said:   9 years ago
@Kala.

If 20 units are remaining then how you can do 20/2 because A had to do all work. So can you explain me that portion?

Kala said:   9 years ago
A -15days
B -10days
LCM - 30
A - 2unit/day
B - 3unit/day

A + B = 5unit/day
They worked for 2days, so 2 * 5 = 10,
Remaining 10 - 30 = 20,
A alone do the remaining in 20 ÷ 2 = 10,
So the total work get completed in 10 + 2 = 12,
Bcoz Already A+B worked for 2days,now A alone in 10 days.
(2)

Raja said:   9 years ago
Guys at last 2 are added. Look at questions carefully. Because the total time to complete the work is asked. Not time is taken by a to complete the job. So total day is 10 + 2=12.

Hope you are done what it now! Cheers.