Aptitude - Time and Work - Discussion
Discussion Forum : Time and Work - General Questions (Q.No. 1)
1.
A can do a work in 15 days and B in 20 days. If they work on it together for 4 days, then the fraction of the work that is left is :
Answer: Option
Explanation:
A's 1 day's work = | 1 | ; |
15 |
B's 1 day's work = | 1 | ; |
20 |
(A + B)'s 1 day's work = | ![]() |
1 | + | 1 | ![]() |
= | 7 | . |
15 | 20 | 60 |
(A + B)'s 4 day's work = | ![]() |
7 | x 4 | ![]() |
= | 7 | . |
60 | 15 |
Therefore, Remaining work = | ![]() |
1 - | 7 | ![]() |
= | 8 | . |
15 | 15 |
Discussion:
344 comments Page 33 of 35.
Meenu said:
6 years ago
Thanks for explaining @Swetha.
Vikaah yadav said:
6 years ago
Thank for the explanation @Vikash.
Pooja said:
6 years ago
How 7/60 came? Please explain me to get it.
Divye said:
6 years ago
A can complete work in 15 days.
B can complete work in 20 days.
total work (in units) = L.C.M of 15 and 20 => 60 units.
Unit work of A = Total work (in units)/Number of days A take to complete work => 60/15 = 4.
Unit work of B = Total work (in units)/Number of days B take to complete work => 60/20 = 3.
Work done in 1 day by A and B together = Unit work done by A + Unit work done by B => 4+3 = 7.
Work done by A and B together in 4 days = Work done by A and B together in 1 day * 4 => 7 * 4=28.
Work left = Total unit of work - work done by A and B together in 4 days => 60 - 28 = 32.
B can complete work in 20 days.
total work (in units) = L.C.M of 15 and 20 => 60 units.
Unit work of A = Total work (in units)/Number of days A take to complete work => 60/15 = 4.
Unit work of B = Total work (in units)/Number of days B take to complete work => 60/20 = 3.
Work done in 1 day by A and B together = Unit work done by A + Unit work done by B => 4+3 = 7.
Work done by A and B together in 4 days = Work done by A and B together in 1 day * 4 => 7 * 4=28.
Work left = Total unit of work - work done by A and B together in 4 days => 60 - 28 = 32.
Rushikesh said:
6 years ago
@Pooja
(1/15)+(1/20).
[(20+15)/(15*20)],
= 35/300,
= 7/60.
(1/15)+(1/20).
[(20+15)/(15*20)],
= 35/300,
= 7/60.
Swetha said:
6 years ago
We know A done his work in 15 days and B in 20 days so total work is we take as 1.work is inversely proportion to days 1÷15 +1÷20=(15+20)/15x20=35/300=7/60=7x4/60=28/60=1-28/60=8/15.
Here 1 indicates total work.
Here 1 indicates total work.
Chandradeepa said:
6 years ago
By considering LCM 60 in that case why should we need to do remaining work divided by total work.
Sufiyan said:
6 years ago
A' work is (1÷15) in one day,
B's work is (1÷20) in one day,
If both perform the work together then (1÷15)+(1÷20)=(35÷300) work is done in one day.
Now multiplying it by 4 so we get the amount of work done in 4 days.
(35÷300)*4 = (7÷15).
Now we know the total amount of work is 1.
Then subtract (1)-(7÷15)=(8÷15) the remaining work.
B's work is (1÷20) in one day,
If both perform the work together then (1÷15)+(1÷20)=(35÷300) work is done in one day.
Now multiplying it by 4 so we get the amount of work done in 4 days.
(35÷300)*4 = (7÷15).
Now we know the total amount of work is 1.
Then subtract (1)-(7÷15)=(8÷15) the remaining work.
Timilsina said:
6 years ago
A=1/15 and b=1/20 ,a+b=7/60*4 =7/15 so,
1-7/15 = 8/15.
1-7/15 = 8/15.
Harsh said:
5 years ago
Can you explain why you have put 1_7/15?
Post your comments here:
Quick links
Quantitative Aptitude
Verbal (English)
Reasoning
Programming
Interview
Placement Papers