Aptitude - Time and Work - Discussion
Discussion Forum : Time and Work - General Questions (Q.No. 1)
1.
A can do a work in 15 days and B in 20 days. If they work on it together for 4 days, then the fraction of the work that is left is :
Answer: Option
Explanation:
A's 1 day's work = | 1 | ; |
15 |
B's 1 day's work = | 1 | ; |
20 |
(A + B)'s 1 day's work = | ![]() |
1 | + | 1 | ![]() |
= | 7 | . |
15 | 20 | 60 |
(A + B)'s 4 day's work = | ![]() |
7 | x 4 | ![]() |
= | 7 | . |
60 | 15 |
Therefore, Remaining work = | ![]() |
1 - | 7 | ![]() |
= | 8 | . |
15 | 15 |
Discussion:
344 comments Page 33 of 35.
Trupti said:
1 decade ago
Thanks Parthiban. I understood well.
Parthiban said:
1 decade ago
@Trupti
1-7/15 = (15-7)/15 = 8/15
I hope this will help you !
1-7/15 = (15-7)/15 = 8/15
I hope this will help you !
Trupti said:
1 decade ago
1-7/15 should be 6/15 please explaine how 8/15......
Rajesh Chowdary said:
1 decade ago
Explanations are good plz share any simple methods other than these
Amrinder said:
1 decade ago
4/60 is ok 4 is no of working and 60 is hours in day
cant undestand 3/60
cant undestand 3/60
Sagar said:
1 decade ago
@deepa
lcm of 15 and 20 is 60 so we get 7/60
understood
lcm of 15 and 20 is 60 so we get 7/60
understood
Sheelu said:
1 decade ago
1/15+1/20=7/60
7/60*4=8/15
7/60*4=8/15
Sundar said:
1 decade ago
@Vijay Kumar
1/15 + 1/20 = ?
1/15 * 4/4 = 4/60 ok.
1/20 * 3/3 = 3/60 ok.
Now,
4/60 + 3/60 = (4+3)/60 = 7/60. Thats all.
I don't know how to explain more simpler than this. Hope you can understand this. Have a nice day!
1/15 + 1/20 = ?
1/15 * 4/4 = 4/60 ok.
1/20 * 3/3 = 3/60 ok.
Now,
4/60 + 3/60 = (4+3)/60 = 7/60. Thats all.
I don't know how to explain more simpler than this. Hope you can understand this. Have a nice day!
Vijay kumar said:
1 decade ago
Can you explain how 7/60 came ?
Analyser said:
1 decade ago
Since work done is 7/15....which is 7 parts out of 15.....
So obviously total work wud be 15/15......which is 1....
Hence we subtract 7/15...from 15/15 or 1..... i.e 1-7/15.
So obviously total work wud be 15/15......which is 1....
Hence we subtract 7/15...from 15/15 or 1..... i.e 1-7/15.
Post your comments here: