Aptitude - Time and Work - Discussion

Discussion Forum : Time and Work - General Questions (Q.No. 1)
1.
A can do a work in 15 days and B in 20 days. If they work on it together for 4 days, then the fraction of the work that is left is :

1
4

1
10

7
15

8
15

Answer: Option
Explanation:

A's 1 day's work = 1 ;
15

B's 1 day's work = 1 ;
20

(A + B)'s 1 day's work = ( 1 + 1 ) = 7 .
15 20 60

(A + B)'s 4 day's work = ( 7 x 4 ) = 7 .
60 15

Therefore, Remaining work = ( 1 - 7 ) = 8 .
15 15

Discussion:
344 comments Page 3 of 35.

Sujit said:   1 decade ago
@Dipen:

Probability is always .....Total chance = 1.

If you say chances of wining a match is 1/2 i.e.(50%) it means chances of losing match is also 1/2 (50%)...how this losing chances 1/2 comes?

It comes from subtracting wining chances from total chance that is : 1-1/2 = 1/2

Similarly in above question

Remaining work = total work (1) - 4 day's work (7/15) = 8/15

Hope you get this...Have a great time :-)

Dipu Ahmed said:   9 years ago
Here,
A works 1/15 in 1 day.
B works 1/20 in 1 day.

So, A + B works (1/15 + 1/20) = 7/60 in 1 day.

So, if A + B works together 7/60 in 1 day.
Then A + B works together (7/60 * 4) = 8/15 in 4 day.

If we assume that 1 is the full work and A+B works together 8/15 in 4 days .
The remaining works we get by {full work - (A + B)'s 4 days completed works}.
So , (1 - 8/15) = 7/15.
So, the answer is 7/15.

Krishna gummani said:   1 decade ago
A can do a work in 15 days.
B can do the work in 20 days.

i.e. in one day the work completed by A and B is 1/15 and 1/20 respectively.
In one day the work done by both A and B is, 1/15+1/20 = 7/60.

If, for one day the work done is 7/60, then for four days?
7/60*4 = 28/60.

The total work is 1.
Work done in 4 days is 28*60.
Then, remaining work is to be done is 1-28/60.

i.e. 8/15.

Hence proved.

Joel said:   4 years ago
Lets take total work is = 1.

In 15 days A will complete the work;

In one day he comlete 1/15 part of work,
Similarly B comletes 1/20 work in one day.

Hence A and B both completes 1/15 + 1/20 work in one day
1/15+1/20 = 7/60.
A and B's one day work,
thier 4 days work = 4 * (7/60) = 28/60 = >7/15,
Now total work is 1,
They completed 7/15 work in 4 days,
Now remaining work is1-7/15 = 8/15.

Dibyanshu said:   3 years ago
A - 15 days.
B - 20 days.

LCM of 15 & 20 is 60 (The total work is 60 also).

So,

The Efficiency of one day's work is 60/15 = 4 and 60/20 = 3.

Then, both A & B can complete the work in one day is 4+3=7.

They worked for 4 days, so 7x4=28
Work completed in 4days by both A+B=28.
Then, rest work = Total work - Completed work
Rest work = 60-28=32.
32/60 = 8/15
The answer is = 8/15.
(233)

Ankit kain said:   8 years ago
Here is the perfect solution.

L.C.M- 60 (it is the lcm of 15 and 20 and here it is total work)

A's---------15 days|---EFFICIENCY-60÷15=4 (because, work= efficiency * time)
B's---------20 days|---EFFICIENCY-60÷20=3

combined efficiency of A and B =7.
work done by (A+B) in 4 days= 7 * 4=28(because work = efficiency * time).
hence ratio---------> 28/60=8/15.

Mahesh Gehlot said:   1 decade ago
7/60 is the total work done by A and B in day 1.
Therefore for 4 days we will calculate as below.

7/60 *4 means when its multiplication we will divide.
ie. 4/15 = 60 and we need to keep 7 integer as it was.

Therefore we get 7/15.

I don't know, Hope you'll understand this.

A simple logic when its + or - we will cross multiply

And when its * we will divide.

Thanks.

RDT said:   1 decade ago
@KARTHIKEYAN and @RAHUL.

DONT CONFUSE.

A can do in 15 days.
A can do it in 1 days = 1/15.

Similarly B can do it = 1/20.
They work totally in a day.

1/15+1/20 = 35/300 = 7/60.

Work done by A and B for 4 days = 4(7/60) = 7/15.

So, Work left = Total work - Work done by A and B.
Therefore, work left = 1-(7/15) = 8/15.

This is the answer.

I hope this helps you.

Thyag said:   1 decade ago
Hi Manoj,

You need to simplify big number 35/300 in to small number for further calculation.

So, you need to divide one common number of both numerator and denominator.

You couldn't select 2, 3 and 4 as a dividing number. But you can use 5 as a common divider.

If you divide 5 in both numerator and denominator, you will get 7/60.

I hope your doubt clarified.

Ram said:   1 decade ago
Hi friends..........
A can do wrk in 15 dayz ;
b Can do wrk in 20 dayz;
then LCM of A&B=7/60;
Explain:
=1/15+1/20
=[(4/4*15)+(3/3*20)]
=(4/60)+(3/60)
=3+4/60
=7/60
If A and B do wrk in 4 day=(7/60 *4 )
=7/15
work is 1 so=1-7/15
=15-7/15
Ans is = 8/15

Its easy for ur understanding...............


Post your comments here:

Your comments will be displayed after verification.