Aptitude - Time and Work - Discussion
Discussion Forum : Time and Work - General Questions (Q.No. 1)
1.
A can do a work in 15 days and B in 20 days. If they work on it together for 4 days, then the fraction of the work that is left is :
Answer: Option
Explanation:
A's 1 day's work = | 1 | ; |
15 |
B's 1 day's work = | 1 | ; |
20 |
(A + B)'s 1 day's work = | ![]() |
1 | + | 1 | ![]() |
= | 7 | . |
15 | 20 | 60 |
(A + B)'s 4 day's work = | ![]() |
7 | x 4 | ![]() |
= | 7 | . |
60 | 15 |
Therefore, Remaining work = | ![]() |
1 - | 7 | ![]() |
= | 8 | . |
15 | 15 |
Discussion:
344 comments Page 27 of 35.
Lohith said:
5 years ago
How (1/15+1/20 )= 7/60? Explain, please.
Mani said:
1 decade ago
Still i have confusion. How 7/60 comes?
Sai kishore said:
1 decade ago
Still I have confusion. How 7/60 comes?
Bhargav said:
10 years ago
I don't understand why we take 1-7/15?
Santhosh said:
8 years ago
Can anyone explain this in LCM method?
NISHA said:
8 years ago
Why sub this (1-7/15) can you explain?
Bha said:
12 months ago
Thanks all for explaining the answer.
(23)
Trupti said:
1 decade ago
Thanks Parthiban. I understood well.
Dhanalakshmi said:
8 years ago
Thanks for your explanation @Swetha.
Priya said:
10 years ago
Can you explain how this 7/15 came?