Aptitude - Time and Work - Discussion
Discussion Forum : Time and Work - General Questions (Q.No. 1)
1.
A can do a work in 15 days and B in 20 days. If they work on it together for 4 days, then the fraction of the work that is left is :
Answer: Option
Explanation:
A's 1 day's work = | 1 | ; |
15 |
B's 1 day's work = | 1 | ; |
20 |
(A + B)'s 1 day's work = | ![]() |
1 | + | 1 | ![]() |
= | 7 | . |
15 | 20 | 60 |
(A + B)'s 4 day's work = | ![]() |
7 | x 4 | ![]() |
= | 7 | . |
60 | 15 |
Therefore, Remaining work = | ![]() |
1 - | 7 | ![]() |
= | 8 | . |
15 | 15 |
Discussion:
344 comments Page 23 of 35.
Merlin said:
1 decade ago
Why do we make an assumption that the total work is 1?
Sushmoy said:
10 years ago
(1-8/15) = 7/15 how is it possible? Please explain me.
Sushant said:
9 years ago
How 7/60 come?
How to solve 1/15 + 1/20? Explain me.
How to solve 1/15 + 1/20? Explain me.
Yona said:
8 years ago
According to me,
=(4/15+4/20),
=(140/300),
=(7/15).
=(4/15+4/20),
=(140/300),
=(7/15).
SkiGi said:
4 years ago
Why 7/60? I don't understand, please someone explain.
Trupti said:
1 decade ago
1-7/15 should be 6/15 please explaine how 8/15......
Sumit sharma said:
10 years ago
Please some one tell how 1/10:1/15:1/20 comes 6:4:3?
Lakshmanan S said:
2 years ago
How come remaining work 1- 7/15? Please explain me.
(71)
Irfan said:
11 months ago
How to find out the remaining work? Please explain.
(43)
Suba said:
1 decade ago
Why we subtract with one? can you please explain.
Post your comments here: