1.
A can do a work in 15 days and B in 20 days. If they work on it together for 4 days, then the fraction of the work that is left is :

1
4

1
10

7
15

8
15

Answer: Option
Explanation:

A's 1 day's work = 1 ;
15

B's 1 day's work = 1 ;
20

(A + B)'s 1 day's work = ( 1 + 1 ) = 7 .
15 20 60

(A + B)'s 4 day's work = ( 7 x 4 ) = 7 .
60 15

Therefore, Remaining work = ( 1 - 7 ) = 8 .
15 15

Discussion:
344 comments Page 12 of 35.

Prashant said:   1 decade ago
@Deepa.

Actually when fraction occur.
Then base must be same while doing it.

1/15 + 1/20 in this situation to calculate it base must be same. We can make it by multiply 1/15 By 4 and 1/20 By 3 so that it will be:

4/60 and 3/60 so.4/60 + 3/60 now we can do calculation result 7/60.

I hope you understand what I mean to say?

Priya said:   1 decade ago
Is there any easy tricks to proceed further?

Krishna gummani said:   1 decade ago
A can do a work in 15 days.
B can do the work in 20 days.

i.e. in one day the work completed by A and B is 1/15 and 1/20 respectively.
In one day the work done by both A and B is, 1/15+1/20 = 7/60.

If, for one day the work done is 7/60, then for four days?
7/60*4 = 28/60.

The total work is 1.
Work done in 4 days is 28*60.
Then, remaining work is to be done is 1-28/60.

i.e. 8/15.

Hence proved.

Kali said:   1 decade ago
1/15 = 4/60.
1/20 = 3/60.

Simply add 4+3 = 7.
And copy the denominator 60.

LCD:
15 = 5x3.
20 = 5x4.

LCD = 5x3x4 = 60.

Vikki ls said:   1 decade ago
Hi sir,

How would you calculate the 7/16*4 for to knowing the 4/15=60 ?

Please tell me sir.

Deepak said:   1 decade ago
Why are using 1-7/15?

Srikanth said:   1 decade ago
In all these problems total work taken as "1" so we have to remove the resulting answer i.e., 7/15 from total work"1" so remaining work is (1-7/15) i.e., 8/15.

Sassy said:   1 decade ago
I'm not getting it at all can someone explain it why 70/60 in the easiest explanation please.

Rohit wadile said:   1 decade ago
(a*b)/a+b = work out.

(15*20)/15+20 = 4.

300/35 = 4.

7/15.

Remaining Work = (1-7/15).

Answer = 8/15.

Mounika said:   1 decade ago
Why 300 will come?


Post your comments here: