Aptitude - Time and Work - Discussion

Discussion Forum : Time and Work - General Questions (Q.No. 17)
17.
A is 30% more efficient than B. How much time will they, working together, take to complete a job which A alone could have done in 23 days?
11 days
13 days

20 3 days
17

None of these
Answer: Option
Explanation:

Ratio of times taken by A and B = 100 : 130 = 10 : 13.

Suppose B takes x days to do the work.

Then, 10 : 13 :: 23 : x     =>     x = ( 23 x 13 )     =>     x = 299 .
10 10

A's 1 day's work = 1 ;
23

B's 1 day's work = 10 .
299

(A + B)'s 1 day's work = ( 1 + 10 ) = 23 = 1 .
23 299 299 13

Therefore, A and B together can complete the work in 13 days.

Discussion:
119 comments Page 3 of 12.

Nishant said:   1 decade ago
Ratio of times taken by A and B = 100:130 = 10:13.

A alone can do his piece of work in 23 days.

Let B takes x days to complete a given work.

A:B = 10:13.

23:B = 10:13.

B = 299:10.

A's 1 day work = 1:23.

B's 1 day work = 10:299.

(A+B) 's 1 day work = 1:23 + 10:299 = 1:13.

So, together they will complete the work in 13 days.

Harish said:   1 decade ago
Had 100:130 confusion too due to misconception of "efficiency". See Physics says efficiency = (work of A/work of B) * 100. But here work is same, so we can use power. So E= (Power of A/Power of B) * 100. As work is same & P=W/T, so E = (time taken by B/time taken by A) * 100=130 So time taken by A:time taken by B :: 130:100.

Mannu said:   8 years ago
A alone takes 23 days to finish a job.

since A is 30% more efficient,
so B takes( A+30%(A) ) days,
i.e.,B takes ( 1.3*A = 1.3*23 ) days to complete it alone [ since A=23],
(A+B)'s one day work = ( 1/23 )+( 1/(1.3*23) ),
(A+B)'s one day work= 1/13.

Hence it takes 13 days for A alone to finish the work.

Naseem Ahmad Saifi said:   10 years ago
A' s 1 day work =1/23......(1).

Now A is 30% faster of B.

So A's 1 day work = 130/100*B's 1 day work.

=> A = 13/10*B......(2).

From 1st and 2nd 13/10*B = 1/23 => B's 1 day work = 10/299......(3).

(A+B)'s 1 day work = 1/23+10/299 = 23/299.

So they complete work in 299/23 i.e. 13 days.

Sai kumar kaveti said:   9 years ago
A usually takes 23 days to finish the work and is 30% more efficient than B.
As per this,B should take = (130%) * (A) ------time to do work.
=> (130/100) * 23 => 1.3 * 23 ==> 29.9.

Now, (A + B) 1 day work = [1/23 - 1/29.9] = 1/13.
Therefore, A & B takes 13 days to finish the work.

Sushruth said:   6 years ago
FROM : @Abhishek - A does the work in 23 days and he is 30% faster also, so B will do that work in (23+ 30% of 23)= 29.9 days.

Now work done in 1 day by A= (1/23) and B=(1/29.9),
work done by A+B in one day = (1/23 + 1/29.9) = 1/13,

So the workdone by A+B will be in 13 days.
(2)

Vivek said:   1 decade ago
A can do whole work in 23 days.

We have ratio 100:130 = 10(b):13(a).

A takes 23x13 to complete a work in 299 days.

Here 299 is total work which A alone can do in 23 days.

So we know total work is 299.

Both can take 10:13 = 23 days.

Total work/together work = 299/23 = 13.

MAGGI said:   8 years ago
@Pallavi.

Ans: remaining amount f work is 1- 1/6 = 5/6.

5/6 is nothing but (1/6) 5. i.e 5 parts of 1/6.

In the question1/6 work takes 2 days and next part 50% faster.

We have 5 parts of 1/6 remaining (5/6) which is done in 5 days, each part of 1/6 takes 1 day (50% fast).

Priti said:   1 decade ago
Say B does the work in x days.
A is 30% more efficient than B.

That means A will do it in x- (30*x/100) which is equal to 23 days.
So,

X-30*x/100=23.

70x=2300.

X=230/7.

So A and B together will work in.

[1/23+7/230]y=1.

Y=230/17=13.53=13 days (approx).

Abhishek said:   6 years ago
A does the work in 23 days and he is 30% faster also, so B will do that work in (23+ 30% of 23)= 29.9 days.
Now work done in 1 day by A= (1/23) and B=(1/29.9),
work done by A+B in one day = (1/23 + 1/29.9) = 1/13,
So the workdone by A+B will be in 13 days.
(1)


Post your comments here:

Your comments will be displayed after verification.