Aptitude - Time and Work - Discussion
Discussion Forum : Time and Work - General Questions (Q.No. 17)
17.
A is 30% more efficient than B. How much time will they, working together, take to complete a job which A alone could have done in 23 days?
Answer: Option
Explanation:
Ratio of times taken by A and B = 100 : 130 = 10 : 13.
Suppose B takes x days to do the work.
Then, 10 : 13 :: 23 : x ![]() |
![]() |
23 x 13 | ![]() |
![]() |
299 | . |
10 | 10 |
A's 1 day's work = | 1 | ; |
23 |
B's 1 day's work = | 10 | . |
299 |
(A + B)'s 1 day's work = | ![]() |
1 | + | 10 | ![]() |
= | 23 | = | 1 | . |
23 | 299 | 299 | 13 |
Therefore, A and B together can complete the work in 13 days.
Discussion:
119 comments Page 1 of 12.
S. Kalyan said:
5 years ago
'A' is 30% more Efficient than 'B' that means
A --------- B
100% -------- 130%
to complete 100% of work 'A' took 23 Days i.e;
100% -----------------> 23 days.
130% -----------------> x days (need to find) 130% = (130/100) & 100% = (100/100).
By Cross Multiplying we get;
(130/100) *23 = x * (100/100).
=> x = (130/100) * (100/100) * 23.
=> x= (299/10) --------------------> This is the B value that we found now substitute these A and B values i.e
(A+B) = (1/23) + (10/299).
After Calculation we'll get;
(A+B) = (23/ 299) = 1/13,
Therefore Answer is 1/13.
That's It.
A --------- B
100% -------- 130%
to complete 100% of work 'A' took 23 Days i.e;
100% -----------------> 23 days.
130% -----------------> x days (need to find) 130% = (130/100) & 100% = (100/100).
By Cross Multiplying we get;
(130/100) *23 = x * (100/100).
=> x = (130/100) * (100/100) * 23.
=> x= (299/10) --------------------> This is the B value that we found now substitute these A and B values i.e
(A+B) = (1/23) + (10/299).
After Calculation we'll get;
(A+B) = (23/ 299) = 1/13,
Therefore Answer is 1/13.
That's It.
(1)
S. Kalyan said:
5 years ago
A is 30% more efficient than B.
This means;
A ------------ B
100%--------- 130%
Now this 100% of work done by A in 23days.
Now
100% ---------------------> 23.
130%----------------------> x.
By Cross Multiplication We get;
100% * x = 23 * 130%,
=> (100/100) * x = 23 * (130/100),
=> x = 23 * (13/10),
=> x= (299/10),
this X work now we got is B's Total Work.
Now Calculate A & B work Together.
ie. (A+B)'s 1 day Work = (1/24) + (10/299)/ LCM is 299.
On Calculating we get answer = 23/299 = 1/13.
So, They Took 13 days to Complete the Work.
This means;
A ------------ B
100%--------- 130%
Now this 100% of work done by A in 23days.
Now
100% ---------------------> 23.
130%----------------------> x.
By Cross Multiplication We get;
100% * x = 23 * 130%,
=> (100/100) * x = 23 * (130/100),
=> x = 23 * (13/10),
=> x= (299/10),
this X work now we got is B's Total Work.
Now Calculate A & B work Together.
ie. (A+B)'s 1 day Work = (1/24) + (10/299)/ LCM is 299.
On Calculating we get answer = 23/299 = 1/13.
So, They Took 13 days to Complete the Work.
(7)
Shahid Basha said:
1 decade ago
Say B does a piece of work in 100 days.
Then as A is 30% more efficient has to complete the work in
100-(30/100)*100=70 days
A's 70 days work = B's 100 days work
so A's 1 day work = B's 100/70 days work
Therefore A's 23 days work = B's 2300/70 days Work
Which implies that 1 work is completed by B in 230/7 days
From this total work done by A & B in 1 day = (1/23)+(7/230)
=(10+7)/230
=17/230
So time taken to complete a work = 230/17=13.529 days
LET ME KNOW IF THIS IS WRONG OR EVEN RIGHT.
Then as A is 30% more efficient has to complete the work in
100-(30/100)*100=70 days
A's 70 days work = B's 100 days work
so A's 1 day work = B's 100/70 days work
Therefore A's 23 days work = B's 2300/70 days Work
Which implies that 1 work is completed by B in 230/7 days
From this total work done by A & B in 1 day = (1/23)+(7/230)
=(10+7)/230
=17/230
So time taken to complete a work = 230/17=13.529 days
LET ME KNOW IF THIS IS WRONG OR EVEN RIGHT.
Elumalai said:
1 decade ago
Hello its very easy ....
see
A is 30% more efficient than B
that means A=130% speed B=100% speed assume, then convert into ratio format because 13:10 it's work, now we can convert to days 10:13 (this ratio for separate man work days)
we must now ratio formula then only we understand
this method
A:B=A:B
also we write A:B::A:B
now apply
10:13::23:X ( Formula A:B::c:d =>A*d=B*c )
now we can solve that
10X=13*23
X=(13*23)/10
now we got X value X =299/10 days for B
B 1 day work is 299/10
then as usually go next steps
see
A is 30% more efficient than B
that means A=130% speed B=100% speed assume, then convert into ratio format because 13:10 it's work, now we can convert to days 10:13 (this ratio for separate man work days)
we must now ratio formula then only we understand
this method
A:B=A:B
also we write A:B::A:B
now apply
10:13::23:X ( Formula A:B::c:d =>A*d=B*c )
now we can solve that
10X=13*23
X=(13*23)/10
now we got X value X =299/10 days for B
B 1 day work is 299/10
then as usually go next steps
Sajan said:
8 years ago
Since A is more efficient, hence the ratio of time taken by A and B is 100:130 Or A:B = 10:13.
A alone can do the whole work in 23 days(time taken by A to complete the whole work)
Let time taken by B to complete the whole work be=x
Since time ratio is already with us, hence
23/x=10/13,
X=23 *13/10,
Hence
A 1day Work = 1/23,
B 1day work=10/23 * 13,
(A+B) 1day work=1/23 + 10/23*13,
(A+B) 1day work=(10+13)/23*13,
(A+B) 1day work=1/13.
Therefore (A + B) takes 13 days to complete the work if they work together.
A alone can do the whole work in 23 days(time taken by A to complete the whole work)
Let time taken by B to complete the whole work be=x
Since time ratio is already with us, hence
23/x=10/13,
X=23 *13/10,
Hence
A 1day Work = 1/23,
B 1day work=10/23 * 13,
(A+B) 1day work=1/23 + 10/23*13,
(A+B) 1day work=(10+13)/23*13,
(A+B) 1day work=1/13.
Therefore (A + B) takes 13 days to complete the work if they work together.
Sushruth said:
6 years ago
A is 30% more efficient than B.
That means A=130% speed B=100% speed assume, then convert into ratio format because 13:10 it's work, now we can convert to days 10:13 (this ratio for separate man work days)
We must now ratio formula then only we understand,
This method.
A:B=A:B.
Also we write A:B::A:B.
Now apply
10:13::23:X ( Formula A:B::c:d =>A*d=B*c ).
Now we can solve that,
10X=13*23.
X=(13*23)/10.
NNow we got X value X =299/10 days for B.
B 1 day work is 299/10.
Then as usually go next steps.
That means A=130% speed B=100% speed assume, then convert into ratio format because 13:10 it's work, now we can convert to days 10:13 (this ratio for separate man work days)
We must now ratio formula then only we understand,
This method.
A:B=A:B.
Also we write A:B::A:B.
Now apply
10:13::23:X ( Formula A:B::c:d =>A*d=B*c ).
Now we can solve that,
10X=13*23.
X=(13*23)/10.
NNow we got X value X =299/10 days for B.
B 1 day work is 299/10.
Then as usually go next steps.
Auditee said:
9 years ago
When A is 30% more efficient than B then,
B's efficiency = 100%.
A's efficiency =130%.
Now,
A takes 23 days to complete 1 or whole job.
A takes 1 day to complete 1/23 job.
According to the question,
130% = 1/23,
1% = 1/23 * 130,
100% = 1*100/23 * 130,
= 10/299 = B's 1-day work.
So, A + B together can do the work in 1 day = (1/23+10/299)
= 23/299 = 1/13.
They can do 1/13 part of the work in 1 day.
So, they can do 1 or whole part of the work in 13 * 1 = 13 days.
Ans: 13 days.
B's efficiency = 100%.
A's efficiency =130%.
Now,
A takes 23 days to complete 1 or whole job.
A takes 1 day to complete 1/23 job.
According to the question,
130% = 1/23,
1% = 1/23 * 130,
100% = 1*100/23 * 130,
= 10/299 = B's 1-day work.
So, A + B together can do the work in 1 day = (1/23+10/299)
= 23/299 = 1/13.
They can do 1/13 part of the work in 1 day.
So, they can do 1 or whole part of the work in 13 * 1 = 13 days.
Ans: 13 days.
Swetha said:
1 decade ago
A can do a work in 100 days
B can do a work in 130 days, since A is 30% more efficient than B.
Take LCM of 100 & 130.i.e 1300
A's per day capacity = 1300/100 = 13
B's per day capacity = 1300/130 = 10
Given that A alone can do the given work in 23 days.
Therefore ,work completed by A alone in 23 days = 13 x 23 = 299
if they work together, their per day capacity = 13 + 10 = 23
both together will complete the given work in 299/23 = 13 days
Ans : 13 days
B can do a work in 130 days, since A is 30% more efficient than B.
Take LCM of 100 & 130.i.e 1300
A's per day capacity = 1300/100 = 13
B's per day capacity = 1300/130 = 10
Given that A alone can do the given work in 23 days.
Therefore ,work completed by A alone in 23 days = 13 x 23 = 299
if they work together, their per day capacity = 13 + 10 = 23
both together will complete the given work in 299/23 = 13 days
Ans : 13 days
Gaurank Verma said:
9 years ago
A can do a work in 23 days.
So,
B can do a work in [ 23 + (30/100)*23] = 29.9 days or ~30 days.
Now,
A------------> 23 days.
B------------> 30 days.
LCM(23,30)= 690 (consider it as whole work).
Hence,
A can do 30 part of a work in 1 day.
B can do 23 part of a work in 1 day.
Therefore,
Both A+B can do 53 part of work in 1 day.
Hence, to finish whole work (i.e., 690) (A + B) will take (690/53) = 13.01 days or ~13 days
So,
B can do a work in [ 23 + (30/100)*23] = 29.9 days or ~30 days.
Now,
A------------> 23 days.
B------------> 30 days.
LCM(23,30)= 690 (consider it as whole work).
Hence,
A can do 30 part of a work in 1 day.
B can do 23 part of a work in 1 day.
Therefore,
Both A+B can do 53 part of work in 1 day.
Hence, to finish whole work (i.e., 690) (A + B) will take (690/53) = 13.01 days or ~13 days
Ab Siddique said:
8 years ago
Here, A's efficiency : B's efficiency = 130:100.
So , A time: B time=100:130 or 10:13.
Now we calculate this,
If A takes 10 days B takes = 13 dyas.
If A takes 1 days B takes = 13/10 days.
If A takes 23 days B takes = (13*23)/10 days =299/10.
So B's 1 day work=10/299 and A's 1 day work=1/23.
So A and B work together = 1/23+299/10 = 1/13.
So total time required to finish this job together = 13 days.
So, answer is 13.
So , A time: B time=100:130 or 10:13.
Now we calculate this,
If A takes 10 days B takes = 13 dyas.
If A takes 1 days B takes = 13/10 days.
If A takes 23 days B takes = (13*23)/10 days =299/10.
So B's 1 day work=10/299 and A's 1 day work=1/23.
So A and B work together = 1/23+299/10 = 1/13.
So total time required to finish this job together = 13 days.
So, answer is 13.
Post your comments here:
Quick links
Quantitative Aptitude
Verbal (English)
Reasoning
Programming
Interview
Placement Papers