7.
A can do a piece of work in 4 hours; B and C together can do it in 3 hours, while A and C together can do it in 2 hours. How long will B alone take to do it?
8 hours
10 hours
12 hours
24 hours
Answer: Option
Explanation:

A's 1 hour's work = 1 ;
4

(B + C)'s 1 hour's work = 1 ;
3

(A + C)'s 1 hour's work = 1 .
2

(A + B + C)'s 1 hour's work = ( 1 + 1 ) = 7 .
4 3 12

B's 1 hour's work = ( 7 - 1 ) = 1 .
12 2 12

Therefore B alone will take 12 hours to do the work.

Discussion:
100 comments Page 9 of 10.

Sireesha said:   1 decade ago
[(b+c)=1/3]-[(a+c)=1/2]

=> b=1/12

=>b's time= 12hrs

SAI said:   1 decade ago
B = A+ (B+C) - (A+C) = 1/4 + 1/3 -1/2 = 1/12.
B = 12.

Sohail said:   7 years ago
How, (7/12 - 1/2) = 1/12?

Explain this step please.

Ashish said:   2 decades ago
Good question. Reasoning is difficult for this one.

Arumugam said:   5 years ago
A = 1/4,
A+b = 1/3.
B = 1/3-1/4 = 1/12.
And = 12.
(6)

Abhin said:   1 decade ago
By the way why we are reciprocating 1/12 into 12?

Shree said:   8 years ago
Clear and detailed explanation. Thank you all.

Anjum said:   10 years ago
Thank you everyone for the clear explanation.

Chiru said:   10 years ago
Thank you everyone for the clear explanation.

Mohit said:   1 decade ago
Why its taken 1/4 and 1/3 ? 4 and 3 why not?