Discussion Forum : Time and Work - General Questions (Q.No. 7)
7.
A can do a piece of work in 4 hours; B and C together can do it in 3 hours, while A and C together can do it in 2 hours. How long will B alone take to do it?
Answer: Option
Explanation:
A's 1 hour's work = | 1 | ; |
4 |
(B + C)'s 1 hour's work = | 1 | ; |
3 |
(A + C)'s 1 hour's work = | 1 | . |
2 |
(A + B + C)'s 1 hour's work = | ![]() |
1 | + | 1 | ![]() |
= | 7 | . |
4 | 3 | 12 |
B's 1 hour's work = | ![]() |
7 | - | 1 | ![]() |
= | 1 | . |
12 | 2 | 12 |
B alone will take 12 hours to do the work.
Discussion:
95 comments Page 10 of 10.
Sam said:
8 years ago
You explained well @Akshay.
Xyx said:
8 years ago
How it will 7/12-1/2=1/12?
(1)
Spoorti said:
4 years ago
Thank you @Bhanu.
(3)
Sukumar said:
7 years ago
Well said @Hindu.
Shro said:
1 decade ago
Thanku hindu:).