7.
A can do a piece of work in 4 hours; B and C together can do it in 3 hours, while A and C together can do it in 2 hours. How long will B alone take to do it?
8 hours
10 hours
12 hours
24 hours
Answer: Option
Explanation:

A's 1 hour's work = 1 ;
4

(B + C)'s 1 hour's work = 1 ;
3

(A + C)'s 1 hour's work = 1 .
2

(A + B + C)'s 1 hour's work = ( 1 + 1 ) = 7 .
4 3 12

B's 1 hour's work = ( 7 - 1 ) = 1 .
12 2 12

Therefore B alone will take 12 hours to do the work.

Discussion:
97 comments Page 7 of 10.

SUREKHA said:   1 year ago
A = 1/4
B + C = 1/3
A+C = 1/2
B =?

A + (B + C) - (A + C) = 1/4 + 1/3 - 1/2
B = 1/12.
B = 12 DAYS.
(16)

Sonu said:   1 decade ago
A=1/4

B+C=1/3

A+C=1/2
----------(subtracting on both sides)
B-A=(-)1/6

B=(- 1/6)+(1/4)

B=1/12

Therefore, 12 hours!!!!

Pavan@9966606261 said:   1 decade ago
Hi friends

b+c=1/3;
a+c=1/2;
a=1/4;
c=1/2-1/4=1/4;
b=1/3-1/4=1/12;

time taken for B alone to complete is 12 hours

Rajin said:   1 decade ago
A = 1/4
B+C = 1/3
A+C = 1/2

A+B+C = 1/4+ 1/3 = 7/12
TO FIND B'W WORK
A+B+C - (A+C) = 7/12 - 1/2 = 1/12

Anil said:   9 years ago
By solving this three equation, we will get the answer.

1/A = 1/4.
1/B + 1/C = 1/3.
1/A + 1/C = 1/2.

Bunny said:   8 years ago
Thank you so much @Himanshi Mishra.

I was looking for this LCM method. This is way too easy. Thanks.

HARRY said:   1 decade ago
C=1/2-1/4=>1/4(C'S 1 DAY WORK)
B=1/3-1/4=>1/12(B'S 1 DAY WORK)
SO 12 DAYS TO COMPLETE THE WORK

ESNALA SIDDA said:   2 months ago
A = 1/4.
B + C = 1/3.
A + C = 1/2.
C = 1/2-1/4.
= 1/4,
B = 1/3 - 1/4.
= 1/12.
=12hrs.
(2)

Lazy Balu said:   6 years ago
A+(B+C)-(C+A) = 1/4+1/3-1/2.
A+B+C-C-A = (3+4-6)/12.

Therefore B = 1/12.
So B can do in 12 days.

Arun said:   1 decade ago
Just simply i know that A's is 1/4
B+C is 1/3
So do it
1/3 - 1/4
And u get 1/12
B's work 12 hour