26.
A and B can do a work in 8 days, B and C can do the same work in 12 days. A, B and C together can finish it in 6 days. A and C together will do it in :
Answer: Option
Explanation:
(A + B + C)'s 1 day's work = | 1 | ; |
6 |
(A + B)'s 1 day's work = | 1 | ; |
8 |
(B + C)'s 1 day's work = | 1 | . |
12 |
![]() |
|
||||||||||||||
|
|||||||||||||||
|
|||||||||||||||
|
So, A and C together will do the work in 8 days.