Discussion Forum : Time and Work - General Questions (Q.No. 2)
2.
A can lay railway track between two given stations in 16 days and B can do the same job in 12 days. With help of C, they did the job in 4 days only. Then, C alone can do the job in:

9 1 days
5

9 2 days
5

9 3 days
5

10
Answer: Option
Explanation:

(A + B + C)'s 1 day's work = 1 ,
4

A's 1 day's work = 1 ,
16

B's 1 day's work = 1 .
12

Therefore C's 1 day's work = 1 - ( 1 + 1 ) = ( 1 - 7 ) = 5 .
4 16 12 4 48 48

So, C alone can do the work in 48 = 9 3 days.
5 5

Discussion:
224 comments Page 6 of 23.

Shimpi said:   1 decade ago
Please help me in 1/4-7/48.

Srikanth said:   1 decade ago
How 48/5 is written as 9*3/5 ?

Sowmya said:   1 decade ago
@Srikanth

9*3/5=(9*5)+3=48/5

Ravi said:   1 decade ago
Thanks uththapa. I get it.

Saquib Ali said:   1 decade ago
You can solve all these sums very fast...

a can do the work in 16 days
b can do the work in 12 days
c can do the work in x days

Calc LCM of 16, 12 and x = 48x

units of work in a day by a = 48x/16 = 3x units
units of work in a day by b = 48x/12 = 4x units
units of work in a day by a = 48x/16 = 48 units

Total units of work in a day = 3x + 4x + 48= 7x+48
Thus in 4 days = 4(7x+48)= 28x+192

Total units of work=48x

Thus,
28x+192=48x
20x=192
x=9 3/5 days.

Meenakshi dhawan said:   1 decade ago
@Saquib Ali.

You have solved it wisely.

Ovii said:   1 decade ago
@aparna

Little help to the explanation of 1's days work.

If A's 1 day work = 1/n than the complete/whole work can be done in n*1 days.

It can be modify to above 1 day's work, e.g

if A's 5 days work = 1/25, than the complete/whole work = 5*25= 125.

Simran said:   1 decade ago
Thanks for the help.

VASUDEVARAO said:   1 decade ago
Thank you nikitha well s. C method thanku.

Swetha said:   1 decade ago
1/12+1/16
=4+3/48
=7/48


Post your comments here: