Aptitude - Time and Work - Discussion

Discussion Forum : Time and Work - General Questions (Q.No. 2)
2.
A can lay railway track between two given stations in 16 days and B can do the same job in 12 days. With help of C, they did the job in 4 days only. Then, C alone can do the job in:

9 1 days
5

9 2 days
5

9 3 days
5

10
Answer: Option
Explanation:

(A + B + C)'s 1 day's work = 1 ,
4

A's 1 day's work = 1 ,
16

B's 1 day's work = 1 .
12

Therefore C's 1 day's work = 1 - ( 1 + 1 ) = ( 1 - 7 ) = 5 .
4 16 12 4 48 48

So, C alone can do the work in 48 = 9 3 days.
5 5

Discussion:
228 comments Page 6 of 23.

Nikita said:   2 decades ago
1/4= 1/12+1/16+1/c
1/4-7/48=1/c
c=9*3/5


1/c= c's one day work

Sunil said:   2 decades ago
Why 48/5 is written? please help me.

Sunaina said:   2 decades ago
Why we should take 16 and 12 as 1/16 and 1/12?

Karthick said:   2 decades ago
Why the fraction 5/48 is changed to 48/5?

Shimpi said:   2 decades ago
Please help me in 1/4-7/48.

Srikanth said:   2 decades ago
How 48/5 is written as 9*3/5 ?

Sowmya said:   2 decades ago
@Srikanth

9*3/5=(9*5)+3=48/5

Ravi said:   2 decades ago
Thanks uththapa. I get it.

Saquib Ali said:   2 decades ago
You can solve all these sums very fast...

a can do the work in 16 days
b can do the work in 12 days
c can do the work in x days

Calc LCM of 16, 12 and x = 48x

units of work in a day by a = 48x/16 = 3x units
units of work in a day by b = 48x/12 = 4x units
units of work in a day by a = 48x/16 = 48 units

Total units of work in a day = 3x + 4x + 48= 7x+48
Thus in 4 days = 4(7x+48)= 28x+192

Total units of work=48x

Thus,
28x+192=48x
20x=192
x=9 3/5 days.

Meenakshi dhawan said:   1 decade ago
@Saquib Ali.

You have solved it wisely.


Post your comments here: