Discussion Forum : Time and Work - General Questions (Q.No. 2)
2.
A can lay railway track between two given stations in 16 days and B can do the same job in 12 days. With help of C, they did the job in 4 days only. Then, C alone can do the job in:

9 1 days
5

9 2 days
5

9 3 days
5

10
Answer: Option
Explanation:

(A + B + C)'s 1 day's work = 1 ,
4

A's 1 day's work = 1 ,
16

B's 1 day's work = 1 .
12

Therefore C's 1 day's work = 1 - ( 1 + 1 ) = ( 1 - 7 ) = 5 .
4 16 12 4 48 48

So, C alone can do the work in 48 = 9 3 days.
5 5

Discussion:
224 comments Page 21 of 23.

Des said:   1 decade ago
How did they get 48 in 7/48?

Yasodha said:   1 decade ago
How to came 4/48 explain it?

Shimpi said:   1 decade ago
Please help me in 1/4-7/48.

Lovely said:   1 decade ago
Why take 1/4 in first step?

Ravi said:   1 decade ago
Thanks uththapa. I get it.

Phani Kumar said:   1 decade ago
Can explain 5/48 has come?

Sonu singh said:   5 years ago
Thanks all for explaining.

Rajasekar said:   1 decade ago
How 5/48 is written 48/5?

Mallik said:   1 decade ago
Reema explained clearly.

Kumar said:   10 years ago
@Amit.

It is addition.