Aptitude - Time and Work - Discussion
Discussion Forum : Time and Work - General Questions (Q.No. 2)
2.
A can lay railway track between two given stations in 16 days and B can do the same job in 12 days. With help of C, they did the job in 4 days only. Then, C alone can do the job in:
Answer: Option
Explanation:
(A + B + C)'s 1 day's work = | 1 | , |
4 |
A's 1 day's work = | 1 | , |
16 |
B's 1 day's work = | 1 | . |
12 |
![]() |
1 | - | ![]() |
1 | + | 1 | ![]() |
= | ![]() |
1 | - | 7 | ![]() |
= | 5 | . |
4 | 16 | 12 | 4 | 48 | 48 |
So, C alone can do the work in | 48 | = 9 | 3 | days. |
5 | 5 |
Discussion:
224 comments Page 21 of 23.
Des said:
1 decade ago
How did they get 48 in 7/48?
Yasodha said:
1 decade ago
How to came 4/48 explain it?
Shimpi said:
1 decade ago
Please help me in 1/4-7/48.
Lovely said:
1 decade ago
Why take 1/4 in first step?
Ravi said:
1 decade ago
Thanks uththapa. I get it.
Phani Kumar said:
1 decade ago
Can explain 5/48 has come?
Sonu singh said:
5 years ago
Thanks all for explaining.
Rajasekar said:
1 decade ago
How 5/48 is written 48/5?
Mallik said:
1 decade ago
Reema explained clearly.
Kumar said:
10 years ago
@Amit.
It is addition.
It is addition.