Discussion Forum : Time and Work - General Questions (Q.No. 2)
2.
A can lay railway track between two given stations in 16 days and B can do the same job in 12 days. With help of C, they did the job in 4 days only. Then, C alone can do the job in:

9 1 days
5

9 2 days
5

9 3 days
5

10
Answer: Option
Explanation:

(A + B + C)'s 1 day's work = 1 ,
4

A's 1 day's work = 1 ,
16

B's 1 day's work = 1 .
12

Therefore C's 1 day's work = 1 - ( 1 + 1 ) = ( 1 - 7 ) = 5 .
4 16 12 4 48 48

So, C alone can do the work in 48 = 9 3 days.
5 5

Discussion:
224 comments Page 16 of 23.

Deepika said:   1 decade ago
How is last step is taken 5/48 is reversed to 48/5?
(1)

Imran said:   7 years ago
Can anyone explain me this question by LCM method?

Ankur said:   8 years ago
How 7/48 come from 1/16+1/12?

Please explain me.

Tamilmani said:   10 years ago
Please answer sir basic formula applied please.

Sidhartha said:   9 years ago
How it come 5/48? Please give a clear solution.

Sunaina said:   1 decade ago
Why we should take 16 and 12 as 1/16 and 1/12?

Emma said:   1 decade ago
Where does 48 come from in this come equation?

Nil said:   3 years ago
How 48/5 is written as 9*3/5? Please explain.
(1)

Helper said:   1 decade ago
We get 1/x=5/48.

Then we want x. So x=48/5.

Temesegen demelash said:   4 months ago
Thanks all for helping me to get the answer.