Aptitude - Time and Work - Discussion

Discussion Forum : Time and Work - Data Sufficiency 2 (Q.No. 2)
Directions to Solve

Each of the questions given below consists of a question followed by three statements. You have to study the question and the statements and decide which of the statement(s) is/are necessary to answer the question.


2.

How many workers are required for completing the construction work in 10 days?

I. 

20% of the work can be completed by 8 workers in 8 days.

II. 

20 workers can complete the work in 16 days.

 III. 

One-eighth of the work can be completed by 8 workers in 5 days.

I only
II and III only
III only
I and III only
Any one of the three
Answer: Option
Explanation:

  I. 20 work can be completed by (8 x 8) workers in 1 day.
100

   Whole work can be completed by (8 x 8 x 5) workers in 1 day.

        = 8 x 8 x 5 workers in 10 days = 32 workers in 10 days.
10


 II. (20 x 16) workers can finish it in 1 day.

   (20 x 16) workers can finish it in 10 days.
10

   32 workers can finish it in 10 days.


III. 1 work can be completed by (8 x 5) workers in 1 day.
8

   Whole work can be completed by (8 x 5 x 8) workers in 1 day.

        = 8 x 5 x 8 workers in 10 days = 32 workers in 10 days.
10

Any one of the three gives the answer.

Correct answer is (E).

Discussion:
5 comments Page 1 of 1.

Yash Patel said:   3 years ago
Let the no of workers be "x"
Work per "x" men per day = 1/10x.
When 5 workers didn't join work per men, per day = 1/(x-5) * 12.
Equating both the above equations we get x = 30.
(2)

Soneram said:   8 years ago
A group of workers estimates to finish a work in 10 days, but 5 workers could not join the work. If the rest of them finished the work in 12 days, the number of members present in the team originally is?

Can anyone answer this?

Teja simhak said:   9 years ago
8 workers took 8 days to complete (20/100 = 1/5)th part of work, ie, 1 day work of 8w = 1/8.

1-day work of 1w = 1/8 * 8.

1/5th part is completed by 8w => 1w part =1/8 * 8 * 5.
1 worker's 1day work is 1/(8 * 8 * 5).
For 10 days work ->10/(8 * 8 * 5) = 1/32.

=> 32 workers are needed to complete 10 days work.
(1)

Shirisha said:   1 decade ago
In first statement explanation (8 x 8 x 5). How 5 came?
(1)

Siddharth Mohan Nair said:   1 decade ago
In the second option it is given that 20 workers can complete the work in 16 days. If we use the cross multiplication method approach, in 1 day, the number of workers required should be (1*20)/ 16. This is wrong. Why is it that this cross multiplication approach does not work here?

Post your comments here:

Your comments will be displayed after verification.