Discussion Forum : Time and Work - General Questions (Q.No. 12)
12.
4 men and 6 women can complete a work in 8 days, while 3 men and 7 women can complete it in 10 days. In how many days will 10 women complete it?
Answer: Option
Explanation:
Let 1 man's 1 day's work = x and 1 woman's 1 day's work = y.
Then, 4x + 6y = | 1 | and 3x + 7y = | 1 | . |
8 | 10 |
Solving the two equations, we get: x = | 11 | , y = | 1 |
400 | 400 |
![]() |
1 | . |
400 |
![]() |
![]() |
1 | x 10 | ![]() |
= | 1 | . |
400 | 40 |
Hence, 10 women will complete the work in 40 days.
Discussion:
106 comments Page 9 of 11.
Manu said:
1 decade ago
Please can you explain how to get x = 11/400 and y = 1/400.
Anushya said:
8 years ago
I can't understand this solution. Anyone help me to get it.
S.p.velu said:
1 decade ago
Can anyone to solve those two equation in step by step?
Suma said:
1 decade ago
Hi, can anybody explain how comes 1/8-6/400 =11/100?
Thanveer said:
4 years ago
You are wrong @Kishor,
Right, Agree with you @Nagu.
Right, Agree with you @Nagu.
Kalyan said:
1 decade ago
Hi can any body say how 11/400 is possible?
Raman said:
1 decade ago
Can anyone please solve this by LCM method?
Saurabh said:
1 decade ago
@Narasingarao please explain your method?
Ashok said:
9 years ago
Please learn how solve this equations?
Sonu said:
7 years ago
Can anyone solve the equation clearly?
Post your comments here: