Aptitude - Time and Work - Discussion
Discussion Forum : Time and Work - General Questions (Q.No. 12)
12.
4 men and 6 women can complete a work in 8 days, while 3 men and 7 women can complete it in 10 days. In how many days will 10 women complete it?
Answer: Option
Explanation:
Let 1 man's 1 day's work = x and 1 woman's 1 day's work = y.
Then, 4x + 6y = | 1 | and 3x + 7y = | 1 | . |
8 | 10 |
Solving the two equations, we get: x = | 11 | , y = | 1 |
400 | 400 |
![]() |
1 | . |
400 |
![]() |
![]() |
1 | x 10 | ![]() |
= | 1 | . |
400 | 40 |
Hence, 10 women will complete the work in 40 days.
Discussion:
106 comments Page 10 of 11.
Sneha said:
2 decades ago
Please help in solving (i) and (ii).
Cln reddy said:
9 years ago
Please explain it in units method.
Umesh said:
8 years ago
Thanks for the complete solutions.
Ashish said:
1 decade ago
Hello, Jyothi. It's my pleasure.
Sangay said:
8 years ago
Superb explanation, thanks @Chan.
Ashok Chandane said:
4 years ago
How to solve these two equations?
(3)
Wasif said:
9 years ago
Why we use days in fraction?
Nagu said:
2 decades ago
You are welcome. Shehina.
Mani said:
1 decade ago
Thanks evry1 for helping.
Suchi said:
7 years ago
Thanks @Chan and @Ashish.
Post your comments here: