Aptitude - Time and Work - Discussion
Discussion Forum : Time and Work - General Questions (Q.No. 3)
3.
A, B and C can do a piece of work in 20, 30 and 60 days respectively. In how many days can A do the work if he is assisted by B and C on every third day?
Answer: Option
Explanation:
A's 2 day's work = | ![]() |
1 | x 2 | ![]() |
= | 1 | . |
20 | 10 |
(A + B + C)'s 1 day's work = | ![]() |
1 | + | 1 | + | 1 | ![]() |
= | 6 | = | 1 | . |
20 | 30 | 60 | 60 | 10 |
Work done in 3 days = | ![]() |
1 | + | 1 | ![]() |
= | 1 | . |
10 | 10 | 5 |
Now, | 1 | work is done in 3 days. |
5 |
Whole work will be done in (3 x 5) = 15 days.
Discussion:
357 comments Page 9 of 36.
Sathish said:
1 decade ago
Hi friends,
we know that whole work completed means we will denote it as 1(full)....
2=1(in 2days full work get completed)
5=1(in 5days full work get completed)
just simple 5=1/2 =>5*2=1(just cross multiple the 2)
we know that whole work completed means we will denote it as 1(full)....
2=1(in 2days full work get completed)
5=1(in 5days full work get completed)
just simple 5=1/2 =>5*2=1(just cross multiple the 2)
Preethi said:
1 decade ago
1/5 of work being done in 3 days. But how do we arrive at the total no. Of days worked by A? what is the logic behind?
Neetu singh said:
1 decade ago
@benny-reli nice explanation.
Harry said:
1 decade ago
1.)days worked by A is 2; 1 day helped by B and C and not A,
2.)given is A's 3 day work
3.)total 1 day work of A,B,C is find
4.)A's 2 day work is found
Result calculation:
A's 3day work=>(1/10)+(1/10)=>A 2day work+A,B,C's 1days)
=>1/5(of whole work) [5 is n]
A's whole work=3*5=15days
2.)given is A's 3 day work
3.)total 1 day work of A,B,C is find
4.)A's 2 day work is found
Result calculation:
A's 3day work=>(1/10)+(1/10)=>A 2day work+A,B,C's 1days)
=>1/5(of whole work) [5 is n]
A's whole work=3*5=15days
Anil said:
1 decade ago
Thanks benny.
Poornima said:
1 decade ago
How can you taking that 3 days? and 1/10+1/10 what is it ?
Imraz said:
1 decade ago
Here 15 days is required for the completion of the work by A, B, C. But in question it is asked 'in how many days can A do the work' - which means the number of days A worked. So to get this we need to divide the 15 by 3 and get '5' as answer.
Can anyone please make me clear if my interpretation is incorrect ?
Can anyone please make me clear if my interpretation is incorrect ?
Ganbrave said:
1 decade ago
@Poornima
A works for 2 days and B,C joins him on 3rd day.
so total combination of them is now 3days
Based on these 3days we can furthur calculate..ok??
A's 2 days work=1/10 and on 3rd day A,B,C together work=1/10
So sum of them gives u total 3days of work done by all of them.
A works for 2 days and B,C joins him on 3rd day.
so total combination of them is now 3days
Based on these 3days we can furthur calculate..ok??
A's 2 days work=1/10 and on 3rd day A,B,C together work=1/10
So sum of them gives u total 3days of work done by all of them.
Rohit said:
1 decade ago
1st day A's + 2nd day A's work = (1/20 + 1/20) = 2/20 = 1/10--(1)
3rd day work is added by B's and C's work so, work done by A+B+C=
(1/20+1/30+1/60) = 1/10--(2)
from (1) and (2)= 1/10+1/10 =1/10
3rd day work is added by B's and C's work so, work done by A+B+C=
(1/20+1/30+1/60) = 1/10--(2)
from (1) and (2)= 1/10+1/10 =1/10
Balalakshmi said:
1 decade ago
Answer explained:
A is working for 2 days alone so A's two day work is first calculated as
A's 2 day work is =1/20*2 = 1/10
Now B and C work with A for only one day(ie 3rd day) and A also working along with B and C in the same 3rd day so A,B and C one day work(ie 3rd day work) is calculated as=(1/20+1/30+1/60)=1/5
Now A's 2 day work+ ABC one day work(ie 3rd day work is calculated)= (1/10+1/10)=1/5
Therefore in 3 days only 1/5 of work is completed
Thus to complete full work 3*5=15 days
(3days=1/5 of full wok completed
3*5 days=full work completed
15 days = full work completed)
A is working for 2 days alone so A's two day work is first calculated as
A's 2 day work is =1/20*2 = 1/10
Now B and C work with A for only one day(ie 3rd day) and A also working along with B and C in the same 3rd day so A,B and C one day work(ie 3rd day work) is calculated as=(1/20+1/30+1/60)=1/5
Now A's 2 day work+ ABC one day work(ie 3rd day work is calculated)= (1/10+1/10)=1/5
Therefore in 3 days only 1/5 of work is completed
Thus to complete full work 3*5=15 days
(3days=1/5 of full wok completed
3*5 days=full work completed
15 days = full work completed)
Post your comments here:
Quick links
Quantitative Aptitude
Verbal (English)
Reasoning
Programming
Interview
Placement Papers