Aptitude - Time and Work - Discussion
Discussion Forum : Time and Work - General Questions (Q.No. 3)
3.
A, B and C can do a piece of work in 20, 30 and 60 days respectively. In how many days can A do the work if he is assisted by B and C on every third day?
Answer: Option
Explanation:
A's 2 day's work = | ![]() |
1 | x 2 | ![]() |
= | 1 | . |
20 | 10 |
(A + B + C)'s 1 day's work = | ![]() |
1 | + | 1 | + | 1 | ![]() |
= | 6 | = | 1 | . |
20 | 30 | 60 | 60 | 10 |
Work done in 3 days = | ![]() |
1 | + | 1 | ![]() |
= | 1 | . |
10 | 10 | 5 |
Now, | 1 | work is done in 3 days. |
5 |
Whole work will be done in (3 x 5) = 15 days.
Discussion:
357 comments Page 6 of 36.
Rohit said:
1 decade ago
1st day A's + 2nd day A's work = (1/20 + 1/20) = 2/20 = 1/10--(1)
3rd day work is added by B's and C's work so, work done by A+B+C=
(1/20+1/30+1/60) = 1/10--(2)
from (1) and (2)= 1/10+1/10 =1/10
3rd day work is added by B's and C's work so, work done by A+B+C=
(1/20+1/30+1/60) = 1/10--(2)
from (1) and (2)= 1/10+1/10 =1/10
Balalakshmi said:
1 decade ago
Answer explained:
A is working for 2 days alone so A's two day work is first calculated as
A's 2 day work is =1/20*2 = 1/10
Now B and C work with A for only one day(ie 3rd day) and A also working along with B and C in the same 3rd day so A,B and C one day work(ie 3rd day work) is calculated as=(1/20+1/30+1/60)=1/5
Now A's 2 day work+ ABC one day work(ie 3rd day work is calculated)= (1/10+1/10)=1/5
Therefore in 3 days only 1/5 of work is completed
Thus to complete full work 3*5=15 days
(3days=1/5 of full wok completed
3*5 days=full work completed
15 days = full work completed)
A is working for 2 days alone so A's two day work is first calculated as
A's 2 day work is =1/20*2 = 1/10
Now B and C work with A for only one day(ie 3rd day) and A also working along with B and C in the same 3rd day so A,B and C one day work(ie 3rd day work) is calculated as=(1/20+1/30+1/60)=1/5
Now A's 2 day work+ ABC one day work(ie 3rd day work is calculated)= (1/10+1/10)=1/5
Therefore in 3 days only 1/5 of work is completed
Thus to complete full work 3*5=15 days
(3days=1/5 of full wok completed
3*5 days=full work completed
15 days = full work completed)
Pavethra said:
1 decade ago
I tell that third day alone A join them so on third day it is 1/20 +1/30+1/60=1/10(here a,b,c all work together)
then 2 days A never join them then B and C work together
then SO 1/20 +1/30=1/5
then make it ulta 10+5=15days
easy na.
then 2 days A never join them then B and C work together
then SO 1/20 +1/30=1/5
then make it ulta 10+5=15days
easy na.
Yashraj said:
1 decade ago
(1/20) + (1/30) + (1/60) = 6/60. Please explain me this step.
Xyz said:
1 decade ago
@Yashraj
When we want to do (1/20)+(1/30)+(1/60) generally, we take the help of L.C.M, But in above case Highest number is 60 which is Divisible by all the remaining number i.e. 20 and 30.
Hence we take L.C.M. as 60 i.e. (3+2+1)/60 becomes 6/60.
Build your Basic maths Strong My friend.
When we want to do (1/20)+(1/30)+(1/60) generally, we take the help of L.C.M, But in above case Highest number is 60 which is Divisible by all the remaining number i.e. 20 and 30.
Hence we take L.C.M. as 60 i.e. (3+2+1)/60 becomes 6/60.
Build your Basic maths Strong My friend.
Rehan said:
1 decade ago
We can consider the avg of the 3 days and calculate for total work only if we know the number of days of their work is a multiple of 3. I mean if they had to work for 14 days, b and c would have assisted them only till day 12. On day 13 and 14 again a would have to work alone.
So how can we take 1/5th of work is done in 3 days?
So how can we take 1/5th of work is done in 3 days?
Mohosin said:
1 decade ago
We can solve it in this way also:
In 1 day, A alone can do 1/20th f the work,
So, in 2 days A can do (1/20 * 2)= 1/10th f the work
On 3rd day A,B and C together do= (1/20 + 1/30 + 1/60)= 6/60= 1/10
___________________________________________________________
Now, after 3 days, total work done= (1/10 + 1/10)=2/10=1/5
so, in 3 days they can complete 1/5th of the work.
so, for completing the whole work, they need (5*3) days= 15days
In 1 day, A alone can do 1/20th f the work,
So, in 2 days A can do (1/20 * 2)= 1/10th f the work
On 3rd day A,B and C together do= (1/20 + 1/30 + 1/60)= 6/60= 1/10
___________________________________________________________
Now, after 3 days, total work done= (1/10 + 1/10)=2/10=1/5
so, in 3 days they can complete 1/5th of the work.
so, for completing the whole work, they need (5*3) days= 15days
Kv manikanta said:
1 decade ago
How do you say that A's work is 2 days it means how it came 2 (1/20) = 1/10.
Hitesh said:
1 decade ago
work done by A per day=1/20;
work done by B per day=1/30;
work done by C per day=1/60;
Let the work is completed in 3x days
So,
1/20*3x+1/30*x+1/60*x=1
=> x=5
=> No. of days required to complete the work=3*5=15days
work done by B per day=1/30;
work done by C per day=1/60;
Let the work is completed in 3x days
So,
1/20*3x+1/30*x+1/60*x=1
=> x=5
=> No. of days required to complete the work=3*5=15days
Anitha said:
1 decade ago
Why we have to calculate A's days work? Explain any one please.