A, B and C can do a piece of work in 20, 30 and 60 days respectively. In how many days can A do the work if he is assisted by B and C on every third day?
Answer: Option
Explanation:
A's 2 day's work = | ![]() |
1 | x 2 | ![]() |
= | 1 | . |
20 | 10 |
(A + B + C)'s 1 day's work = | ![]() |
1 | + | 1 | + | 1 | ![]() |
= | 6 | = | 1 | . |
20 | 30 | 60 | 60 | 10 |
Work done in 3 days = | ![]() |
1 | + | 1 | ![]() |
= | 1 | . |
10 | 10 | 5 |
Now, | 1 | work is done in 3 days. |
5 |
Whole work will be done in (3 x 5) = 15 days.
Discussion:
357 comments Page 36 of 36.
Bala said:
1 decade ago
I can't get this.
Sushant said:
1 decade ago
(A + B + C)'s 1 day's work = 1 + 1 + 1 = 6 = 1 .
20 30 60 60 10
how did we get 60
20 30 60 60 10
how did we get 60
Nitesh Nandwana said:
1 decade ago
Hi chirag don't go on step, here our aim is to compute total work done in 3 days once, first 2 days A is working alone and last 3rd day we are adding work's of B and C.
Abhishek said:
1 decade ago
@chirag:
Step 3 gives work done in first 3 day i.e. work done in 1st day + work done in 2nd day +work done in 3rd day = 1/20 (by A alone) + 1/20 (by B alone) + 1/10 (done by A, B and C together)
Similarly they continue and as per the question on every 3rd day A is joined by B and C.
Step 3 gives work done in first 3 day i.e. work done in 1st day + work done in 2nd day +work done in 3rd day = 1/20 (by A alone) + 1/20 (by B alone) + 1/10 (done by A, B and C together)
Similarly they continue and as per the question on every 3rd day A is joined by B and C.
Satyendra Sharma said:
2 decades ago
3 days work = 1/5
it means 1 day work =1/15
that is 1/15 work is done in 1 Day
now 4/5 part of work that is (1-1/5) will be done in :15*4/5 =12 days....
Hence total work done will done in (12 + 3 ) days...
it means 1 day work =1/15
that is 1/15 work is done in 1 Day
now 4/5 part of work that is (1-1/5) will be done in :15*4/5 =12 days....
Hence total work done will done in (12 + 3 ) days...
(1)
Vinoth said:
2 decades ago
How do you know total working day is 3 (last step).
(1)
Chirag Lakhani said:
2 decades ago
How step 3 is make 1/10+1/10? please explain it.
Post your comments here:
Quick links
Quantitative Aptitude
Verbal (English)
Reasoning
Programming
Interview
Placement Papers