3.
A, B and C can do a piece of work in 20, 30 and 60 days respectively. In how many days can A do the work if he is assisted by B and C on every third day?
12 days
15 days
16 days
18 days
Answer: Option
Explanation:

A's 2 day's work = 1 x 2 = 1 .
20 10

(A + B + C)'s 1 day's work = 1 + 1 +1 = 6 = 1 .
20 30 60 60 10

Work done in 3 days = 1 + 1 = 1 .
10 10 5

Now, 1 work is done in 3 days.
5

Whole work will be done in (3 x 5) = 15 days.

Discussion:
357 comments Page 33 of 36.

Bralow said:   1 decade ago
Why we multiply 3*5 in last step?

Mir sakib said:   1 decade ago
What is its mean every third day?

Jayshri said:   6 years ago
How got the 3rd step (1/10+1/10)?

Chitra.G said:   1 decade ago
Why we take 2 days? Please help.

Shanmugapriya said:   8 years ago
Nice explanation, Thanks @Vijay.

RAJA said:   5 months ago
Why have to take 3 days of work?
(18)

Amey said:   1 decade ago
Why we are multiplying 3 by 5 ?

Nazam said:   7 years ago
How did (1/10+1/10) = 1/5 came?

Ashwini said:   1 decade ago
Can you explain how 6/60 came?

Priya said:   10 years ago
How to solve (1/20+1/30+1/60)?