3.
A, B and C can do a piece of work in 20, 30 and 60 days respectively. In how many days can A do the work if he is assisted by B and C on every third day?
12 days
15 days
16 days
18 days
Answer: Option
Explanation:

A's 2 day's work = 1 x 2 = 1 .
20 10

(A + B + C)'s 1 day's work = 1 + 1 +1 = 6 = 1 .
20 30 60 60 10

Work done in 3 days = 1 + 1 = 1 .
10 10 5

Now, 1 work is done in 3 days.
5

Whole work will be done in (3 x 5) = 15 days.

Discussion:
357 comments Page 30 of 36.

Nike said:   8 years ago
We have A work 2 days alone third-day B&C are added that means A+A+ (A+B+C) THIS is 3days work.

So A can do 2days work=1/10, and A+B+C 1day work=1/10, so add 1/10+1/10=1/5then total day work by A is 3*5=15.

Anuj said:   8 years ago
Nice explanation, Thanks.

Divya said:   8 years ago
Simply;

A's 3 days works ----- 3/20.
B and C join on 3rd day so;
(A+B+C)'s 3 days work will be ---- 3/20 +1/30+ 1/60 = 12/60 = 1/5.
3 days work -- 1/5 then;
1 day work -- 1/15 part of 1 work (i.e 1/15 work in 1 days),
15 days = 1 work.

Akshay said:   8 years ago
Take LCM ot 20,30 and 60 you will get total units of work i.e 360 units.
Now find the 1 day work by using UNITS/DAYS.
A=18 units
B=12 units
C=6 units
Now A+B+C 1 day work is 18+12+6=36 units.
A+B+C will complete the work in 10 days(360/36).

Now, B and C joins every 3rd day which means A will work for 2 days alone and A+B+C will work on the 3rd day.

A 1day work = 18,
A 2 day work= 18*2=36 units,
A+B+C 1 day work is 36 units,
So 3 days of work =36+36= 72 units,
So 1-day work will be 72/3.

Now total work was 360 units.
Total days= 360*3/72 = 15 Days.

Rizwan said:   8 years ago
How this 2 step comes 1/60? explain please.

Kapil dev said:   8 years ago
day-1, day-2, day-3.
A. A. A+B+C.

Every 3rd-day b & c joining.

So 3(3A+B+C)=3(1/20)+1/30+1/60,
=9+2+1/60,
=1/5,
3A+B+C=1/3*5.
=1/15.
15 days work is complited.

Vaibhav More said:   8 years ago
As A does work in 20 days.
B does in 30 days.
C does in 60 days.

Take the lcm and you will get total work = 60 parts.
No of parts A does work = 60/20 = 3 part / day.
Similarly B = 2 parts /day and c= 1 parts/day.
If A does work for 2 days he covers 3+3 parts = 6 parts.
And every third day B & C joins and then A + B +C = 6 parts on 3rd day.
Total work from first day to third day = 6 + 6 parts= 12 parts.
Total work = 60 parts.

Therefore no of days require = 5 * 3 = 15 days.

Sangi said:   7 years ago
Why 3 is multiplied with 5 at last?

Please explain.

Anu said:   7 years ago
I really didn't get the last step where they said whole work will be done in 15 days. Can anyone explain how it comes?

Manisha said:   7 years ago
A work in one day=1/20,
B work in one day=1/30,
C work in one day=1/60.

as A work for 2 days and then on third day B and C do work.
total work done in three days = A 3 days work+B 1 day work+ C one day work,
=3/20+1/30+1/60,
=9/60+2/60+1/60
=12/60.

Total work done in three days =1/5.
3=1/5part.

Let x days required to complete work=1 part.

3/x=1/5/1.
x=3*5=15 days.