Aptitude - Time and Work - Discussion

Discussion Forum : Time and Work - General Questions (Q.No. 3)
3.
A, B and C can do a piece of work in 20, 30 and 60 days respectively. In how many days can A do the work if he is assisted by B and C on every third day?
12 days
15 days
16 days
18 days
Answer: Option
Explanation:

A's 2 day's work = 1 x 2 = 1 .
20 10

(A + B + C)'s 1 day's work = 1 + 1 +1 = 6 = 1 .
20 30 60 60 10

Work done in 3 days = 1 + 1 = 1 .
10 10 5

Now, 1 work is done in 3 days.
5

Whole work will be done in (3 x 5) = 15 days.

Discussion:
357 comments Page 25 of 36.

Jansi said:   1 decade ago
@Sami.

Dear friend A is assisted with B & C every 3rd day, Means first 2 days A is doing work lonely.

Sami said:   1 decade ago
Hi.

Can you explain me that how do you get A's 2 days work?

Praveen.M said:   1 decade ago
Hey guys I have done this way, correct me if I'm wrong.

Let total work be 100%.

A does 5%work in a day (1/20*100).

B does 1/30*100 i.e. 3.3%work.

And like wise C does 1.6% of work.

A completes 10% work in 2 days and on 3rd day he is assisted by B and C hence on 3rd day A does 15%of work and total work on 3rd day is 15%+3.3%+1.6% total is 19.9% so total time is 100/19.9*3 = 15.

Shakti said:   1 decade ago
Let total work = 60.

A's effi.=3, same as B and C have 2 and 1.

Then work

1st 2nd 3rd
3 3 6

Total work in 3 days 12 and hence they take 15 days to complete the work(60).

Nitish Mehta said:   1 decade ago
@Liza. What will you do after calculate 6/60?

Complete your answer.

Liza said:   1 decade ago
In 1/20+1/30+1/60 we take LCM of 20, 30, 60 i.e. 60 then,

60/20 = 3.
60/30 = 2.
60/60 = 1 then,

3+2+1 = 6.

So 6/60. Got it.

Siddalingaswamy c said:   1 decade ago
1/20+1/30+1/60=6/60. Can any one say the 6 came in 6/60?

Bond said:   1 decade ago
1/5 of work --->3 days.

1 complete work ---> ?

= (1*3)/(1/5).

= 15 days.

Arijit Roy said:   1 decade ago
It would be better if it is done in this way.

B, C assist A on the 3rd day so directly we get,

3/20(3 day's of A) + 1/30(assistance of B) + 1/60(assistance of C) = 1/5.

So 1/5 done in 3 days whole is done in 15 days.

Ganesh said:   1 decade ago
Guys, as per my understanding,

1st day A complete 1/20th of work.

2nd day A completes 2/20th of work.

3rd day A along with B and C completes (3/20+1/30+1/60) i.e., 1/5th of the work.

Could some one explain how to calculate?

4th day of A's work ?

5th day of A's work?

6th day of A along with B and C ?


Post your comments here:

Your comments will be displayed after verification.