3.
A, B and C can do a piece of work in 20, 30 and 60 days respectively. In how many days can A do the work if he is assisted by B and C on every third day?
12 days
15 days
16 days
18 days
Answer: Option
Explanation:

A's 2 day's work = 1 x 2 = 1 .
20 10

(A + B + C)'s 1 day's work = 1 + 1 +1 = 6 = 1 .
20 30 60 60 10

Work done in 3 days = 1 + 1 = 1 .
10 10 5

Now, 1 work is done in 3 days.
5

Whole work will be done in (3 x 5) = 15 days.

Discussion:
357 comments Page 19 of 36.

Chittu said:   10 years ago
B and C can complete this work in 20 days.

B and C one day work will be = (1/20).

Instead of assuming every third day B and C will join A in work, let us reduce the efficiency of B and C by 3 so this makes B and C one day as 1/60.

So now doing the calculations.

(1/20)+(1/60) = 1/15. Hence they can complete the work in 15 days.

Please let me know in case of any clarifications needed.

Chirag gupta said:   10 years ago
I read this but understood nothing please explain in easiest way.

Shivam said:   10 years ago
Let n be the no. of total days required;

A's one day work = 1/10.

B's = 1/30, C's = 1/60.

So n(1/10)+n/3(1/30+1/60) = 1.

From here, we get n = 15.

Siddhu said:   10 years ago
Here a work can be completed in by A in 20 days and on third day B and C assist that means A should work for 14 days and remaining 6 days work is assisted by B and C. So help me solve in this way.

Akash said:   10 years ago
Hey why in last we multiplied 1/5 with 3?

Priya said:   10 years ago
How to solve (1/20+1/30+1/60)?

Parth said:   10 years ago
What is the Mean assisted in this question?

Praveen said:   10 years ago
1/5x100-20 percent work done in 3 days therefore for 100 cross multiply 15 days.

Nitin said:   10 years ago
A = 20 = 1 day work of A = 3 LCM = 60.

B = 30 = 1 day work of B = 2.

C = 60 = 1 day work of C = 1.

Day 1 2 3 1 2 3.

Work 3 3 (A+B+C = 3+2+1).

Work of 3 days = 2(A) + (A+B+C).

2*3+(3+2+1) = 12.

3 days = 12 unit work (which number we multiply both side that do not greater than the total unit work).

3*5 days = 12*5 unit work.

15 days = 60 unit.

Onkar said:   10 years ago
A can complete a work in 20 days, B can complete the same work in 30 days and with the help of C together if they complete the work in 60 days, so assume total work to be done is 60. (LCM of 20, 30, 60).

Persons A B C per 3 day.

Days- 20 30 60 12 = 6+6.

Work/day- 3 2 1 5.

----------------------------------------------------------------.

Work - 60 60 60 60.

Per 3 day ----> 12.

How many ----> 60 = (60*3)/12 = 15 days required.

Days required.