Aptitude - Time and Work - Discussion

Discussion Forum : Time and Work - General Questions (Q.No. 3)
3.
A, B and C can do a piece of work in 20, 30 and 60 days respectively. In how many days can A do the work if he is assisted by B and C on every third day?
12 days
15 days
16 days
18 days
Answer: Option
Explanation:

A's 2 day's work = 1 x 2 = 1 .
20 10

(A + B + C)'s 1 day's work = 1 + 1 +1 = 6 = 1 .
20 30 60 60 10

Work done in 3 days = 1 + 1 = 1 .
10 10 5

Now, 1 work is done in 3 days.
5

Whole work will be done in (3 x 5) = 15 days.

Discussion:
357 comments Page 18 of 36.

Arun said:   1 decade ago
How to make first step?

Sudha said:   1 decade ago
Is there any other simple trick to solve this?

Vishal grade said:   1 decade ago
A's 1 day work = 5%.
B's 1 day work = 3.33%.
C's 1 day work = 1.66%.

A, B and C' 1 day work = 5+3.3+1.6 = 10%.
On 1st 2 days total work = 5+5 = 10%.

On 3rd day total work(by all 3)=10%.
In 3 day total work done=10+10=20%.

20% work done in ---- 3 days.
100% work done in --- 15 days.

Divyanshu Dwivedi said:   1 decade ago
It is much easier by this method :

1/20 + 1/(30*3) + 1/(60*3) = 1/x.

1/20 + 1/90 + 1/180 = 1/x.

12/180 = 1/x.

x = 15 Ans.

Psyco said:   1 decade ago
1/5th work done in 3 days.
5/5th of work will be done in x days so,

1/5---3.
5/5---x.

x=3*5*5/5.
x=15.

Golu said:   1 decade ago
Why we are calculating 2 days of work A?

Chitra said:   1 decade ago
Work done in 3 days = 1/5.

Work done in next 3 days = 1/5+1/5.

Work done in 5 days = 1/5+1/5+1/5+1/5+1/5 = 5/5 = 1 (task completed).

Hence 3*5 is used.

Mir sakib said:   1 decade ago
What is its mean every third day?

Ajit said:   1 decade ago
Why multiply 1/20*2?

Vijay said:   1 decade ago
B and C joined with A for every 3 days.

So their (A,B,C) 3 days work is == (A's 2 days work i.e. [1/10]) + (A+B+C 's 1 day work i.e [1/10]).

= 1/10+1/10 = 1/5.

So for 3 days 1/5 work is done.

So total work will complete in 15 days.