Aptitude - Time and Work - Discussion
Discussion Forum : Time and Work - General Questions (Q.No. 3)
3.
A, B and C can do a piece of work in 20, 30 and 60 days respectively. In how many days can A do the work if he is assisted by B and C on every third day?
Answer: Option
Explanation:
A's 2 day's work = | ![]() |
1 | x 2 | ![]() |
= | 1 | . |
20 | 10 |
(A + B + C)'s 1 day's work = | ![]() |
1 | + | 1 | + | 1 | ![]() |
= | 6 | = | 1 | . |
20 | 30 | 60 | 60 | 10 |
Work done in 3 days = | ![]() |
1 | + | 1 | ![]() |
= | 1 | . |
10 | 10 | 5 |
Now, | 1 | work is done in 3 days. |
5 |
Whole work will be done in (3 x 5) = 15 days.
Discussion:
357 comments Page 17 of 36.
Pawan choudhary said:
1 decade ago
Why the first step I don't understand please explain me?
Aby said:
1 decade ago
Please explain the 3rd step.
Susi said:
1 decade ago
A's 2 days work: (1/20*2).
Answer: 1/10.
A, B, C add 1 days work. (1/20 add 1/30 add 1/60).
Answer: (110/36000).(110/2/36000/600).
Answer: (5 add 1/60).
Answer: 1(1/10).
Three days work (1/10 Add 1/10).
Answer (1/5)*3.
Answer: 16.
Answer: 1/10.
A, B, C add 1 days work. (1/20 add 1/30 add 1/60).
Answer: (110/36000).(110/2/36000/600).
Answer: (5 add 1/60).
Answer: 1(1/10).
Three days work (1/10 Add 1/10).
Answer (1/5)*3.
Answer: 16.
Neha Sharma said:
1 decade ago
Why you are multiply 3*5? And in third step why 1/10 is taken in two times? Please exlain it?
Saraswati said:
1 decade ago
Another method to solve this problem:
A can do the work in 1 day = 1/20.
A can do the work in 2 days = 1/20*2 = 1/10.
B+C can do the work in 1 day = 1/30+1/60 = 1/20.
B+C can do the work in 3 days = 1/20*3 = 3/20.
A is assisted by B and C on every third day.
So that 1/20+3/20 = 1/5 (1 days work of A+3 days work of B and C).
Now, 1/5 work is done in 3 days,
Therefore whole work will be done in (3*5) = 15 days.
A can do the work in 1 day = 1/20.
A can do the work in 2 days = 1/20*2 = 1/10.
B+C can do the work in 1 day = 1/30+1/60 = 1/20.
B+C can do the work in 3 days = 1/20*3 = 3/20.
A is assisted by B and C on every third day.
So that 1/20+3/20 = 1/5 (1 days work of A+3 days work of B and C).
Now, 1/5 work is done in 3 days,
Therefore whole work will be done in (3*5) = 15 days.
Sandhu said:
1 decade ago
Sir I can't understand the calculation of 1\20+1\30+1\60 please tell me.
BINDU said:
1 decade ago
Here 1/5 is calculated considering ABC together but here we have to fine work done by A?
Lallitha said:
1 decade ago
In given question, A is assisted on every 3rd days but you all doing for one 3rd day?
Can anyone explain?
Can anyone explain?
Vipul said:
1 decade ago
Work of 1 day = 1/20+1/30+1/60= 6/60= 1/10.
It means that 1/10th part of work is done in 1 day.
(It means 10% work per day).
Now every 3rd day B And C performs -ve work i.e,
Work of every 3rd day = 1/20- 1/30-1/60 = 0/60 = 0.
Days 1 2 3 4 5 6 7 8 9 10 11 12 13 14.
Work% 10+10+0+10+10+0+10+10+0+10+10+0+10+10 = 100%.
Hence work will complete in 14 days.
Note: You can consider day 15 because in day 15 the work done will 0%.
So more correct answer will 14 days.
It means that 1/10th part of work is done in 1 day.
(It means 10% work per day).
Now every 3rd day B And C performs -ve work i.e,
Work of every 3rd day = 1/20- 1/30-1/60 = 0/60 = 0.
Days 1 2 3 4 5 6 7 8 9 10 11 12 13 14.
Work% 10+10+0+10+10+0+10+10+0+10+10+0+10+10 = 100%.
Hence work will complete in 14 days.
Note: You can consider day 15 because in day 15 the work done will 0%.
So more correct answer will 14 days.
Satish kumar said:
1 decade ago
How will make step 3 (1/10+1/10) explain?
Post your comments here:
Quick links
Quantitative Aptitude
Verbal (English)
Reasoning
Programming
Interview
Placement Papers