Aptitude - Time and Work - Discussion

Discussion Forum : Time and Work - General Questions (Q.No. 16)
16.
X and Y can do a piece of work in 20 days and 12 days respectively. X started the work alone and then after 4 days Y joined him till the completion of the work. How long did the work last?
6 days
10 days
15 days
20 days
Answer: Option
Explanation:

Work done by X in 4 days = 1 x 4 = 1 .
20 5

Remaining work = 1 - 1 = 4 .
5 5

(X + Y)'s 1 day's work = 1 + 1 = 8 = 2 .
20 12 60 15

Now, 2 work is done by X and Y in 1 day.
15

So, 4 work will be done by X and Y in 15 x 4 = 6 days.
5 2 5

Hence, total time taken = (6 + 4) days = 10 days.

Discussion:
68 comments Page 6 of 7.

Lakshit said:   7 years ago
@Shweta.

Can you please elaborate last line?

Shree said:   8 years ago
Clear and detailed explanation. Thank you.

Akhil said:   1 decade ago
Can anyone explain this problem clearly.

Nagaraising said:   2 decades ago
Please explain about remaining work?.

Sree said:   1 decade ago
How 6+4?y should we add. Please help.

Shehina.s.p said:   2 decades ago
Please explain how {15/2*4/5} comes?
(1)

Lydia said:   1 decade ago
Please explain the remaining work.

Shanaya said:   4 years ago
Can you please explain 4/5 * 15/2?
(2)

Shanmugam said:   9 years ago
(1-1/5) = 4/5? Please explain it.
(1)

Akil Prakash said:   7 years ago
Thank you @Inna Reddy Chilakala.


Post your comments here:

Your comments will be displayed after verification.