Aptitude - Time and Work - Discussion
Discussion Forum : Time and Work - General Questions (Q.No. 8)
                   
                                       
                                8.
A can do a certain work in the same time in which B and C together can do it. If A and B together could do it in 10 days and C alone in 50 days, then B alone could do it in:
 
                                    Answer: Option
                                                    Explanation:
                                                
| (A + B)'s 1 day's work = | 1 | 
| 10 | 
| C's 1 day's work = | 1 | 
| 50 | 
| (A + B + C)'s 1 day's work = | ![]()  | 
    1 | + | 1 | ![]()  | 
    = | 6 | = | 3 | . .... (i) | 
| 10 | 50 | 50 | 25 | 
A's 1 day's work = (B + C)'s 1 day's work .... (ii)
| From (i) and (ii), we get: 2 x (A's 1 day's work) = | 3 | 
| 25 | 
  A's 1 day's work = | 
    3 | . | 
| 50 | 
  B's 1 day's work | 
    ![]()  | 
    1 | - | 3 | ![]()  | 
    = | 2 | = | 1 | . | 
| 10 | 50 | 50 | 25 | 
So, B alone could do the work in 25 days.
Discussion:
147 comments Page 9 of 15.
                
                        Anil said: 
                         
                        9 years ago
                
                1/A + 1/B = 1/10 --->(1)
1/B + 1/C = 1/A --->(2)
C = 1/50 --->(3)
Just solve this three equation and you will get answer as B = 1/25.
                1/B + 1/C = 1/A --->(2)
C = 1/50 --->(3)
Just solve this three equation and you will get answer as B = 1/25.
                        Imran said: 
                         
                        7 years ago
                
                A+B=1/10. -----> (1)
A+B+C=(1/10 + 1/50) = 3/25.
A+A=3/25......(A = B+C).
A=3/50,
3/50 + B=1/10,
B=1/25,
B alone does it in 25 days.
                A+B+C=(1/10 + 1/50) = 3/25.
A+A=3/25......(A = B+C).
A=3/50,
3/50 + B=1/10,
B=1/25,
B alone does it in 25 days.
                        Vikram sihag said: 
                         
                        1 decade ago
                
                Efficency of a+b = 10%.
Efficency of c = 2%.
Efficency of a+b+c = 12%.
Put up a = b+c.
2(b+c) = 12%.
b = 4%
Days = 100/4 = 25.
                Efficency of c = 2%.
Efficency of a+b+c = 12%.
Put up a = b+c.
2(b+c) = 12%.
b = 4%
Days = 100/4 = 25.
                        Pavan said: 
                         
                        7 years ago
                
                A = B+C.
A+B = 1/10.
C = 1/50.
A+B+C = 6/50.
we know that A = B+C.
B+C+B+C = 6/50,
B = 1/25,
B takes 25 days to complete the work.
                A+B = 1/10.
C = 1/50.
A+B+C = 6/50.
we know that A = B+C.
B+C+B+C = 6/50,
B = 1/25,
B takes 25 days to complete the work.
                        Sudip said: 
                         
                        2 years ago
                
                Short and Simple:
a+b=10, c=50, total work 50.
perday a + b = 5, c = 1.
a+b = 5,
b+c+b = 5,
2b+c = 5,
b = 2/d.
b = 50/2 = 25.
                a+b=10, c=50, total work 50.
perday a + b = 5, c = 1.
a+b = 5,
b+c+b = 5,
2b+c = 5,
b = 2/d.
b = 50/2 = 25.
                     (25)
                
            
                        Pavan@9966606261 said: 
                         
                        1 decade ago
                
                A=B+C;
A+B=1/10;
A-B=1/50;
2A=1/10+1/50=6/50;
A=3/50;
A-B=1/50;
B=3/50-1/50;
B=1/25;
B ALONE CAN DO IN "25" DAYS
                A+B=1/10;
A-B=1/50;
2A=1/10+1/50=6/50;
A=3/50;
A-B=1/50;
B=3/50-1/50;
B=1/25;
B ALONE CAN DO IN "25" DAYS
                        Shubham Uttam Bandgar said: 
                         
                        3 years ago
                
                If A = B+C.
So A-B =C.
i,e A-B = 1/50 ----> eq 1
And
A+B = 1/10 ----> eq 2.
From eq 2 - eq 1 we will get the answer.
.
                So A-B =C.
i,e A-B = 1/50 ----> eq 1
And
A+B = 1/10 ----> eq 2.
From eq 2 - eq 1 we will get the answer.
.
                     (25)
                
            
                        Neil said: 
                         
                        1 decade ago
                
                A=B+C.
A+B+C = 1/10+1/50=6/50.
(B+C)+B+C = 2B+2C=6/50.
B+C = 6/100.
B = 6/100-1/50 = 1/25.
Therefore, B = 25 days.
                A+B+C = 1/10+1/50=6/50.
(B+C)+B+C = 2B+2C=6/50.
B+C = 6/100.
B = 6/100-1/50 = 1/25.
Therefore, B = 25 days.
                        Sun said: 
                         
                        1 decade ago
                
                A+b=10..2
c=1/50
sub (1) in (2)
2b+c=1/10
2b+1/50=1/10
2b=1/10-1/50
2b=5-1/50
2b=4/50
2b=2/25
b=25...
Hence proved
                c=1/50
sub (1) in (2)
2b+c=1/10
2b+1/50=1/10
2b=1/10-1/50
2b=5-1/50
2b=4/50
2b=2/25
b=25...
Hence proved
                        Esayas said: 
                         
                        1 decade ago
                
                If (a+b) = 1/10 and a = b+c, so 2b++c = 1/10.
2b+1/50 = 1/10.
b = 1/25.
So b can finish the work in 25 days.
                2b+1/50 = 1/10.
b = 1/25.
So b can finish the work in 25 days.