A can do a certain work in the same time in which B and C together can do it. If A and B together could do it in 10 days and C alone in 50 days, then B alone could do it in:
15 days
20 days
25 days
30 days
Answer: Option
Explanation:

(A + B)'s 1 day's work = 1
10

C's 1 day's work = 1
50

(A + B + C)'s 1 day's work = 1 + 1 = 6 = 3 . .... (i)
10 50 50 25

A's 1 day's work = (B + C)'s 1 day's work .... (ii)

From (i) and (ii), we get: 2 x (A's 1 day's work) = 3
25

A's 1 day's work = 3 .
50

B's 1 day's work 1 - 3 = 2 = 1 .
10 50 50 25

So, B alone could do the work in 25 days.

Discussion:
148 comments Page 6 of 15.

Nagu said:   1 decade ago
Hi Guys, sorry for the late and here is the explanation about you doubt.

In my previous explanation I mentioned

(a+b+c)'s one day work = 3/25
and a+b+c = 2a here b+c=a means a's one day work = b+c's one day work
then a's one day work+(b+c)'s one day work = 3/25
so a+a = 3/25
2a = 3/25
so here 2* a's one days work = 3/25

So I think u can under stand now

keep practicing.....

DHARMENDRA said:   1 decade ago
A=B+C-----------------(1)
A+B=1/10--------------(2)
C=1/50----------------(3)
(1)+(2)
(B+C)+B=1/10-----------(4)
(3)+(4)
B+(1/50)+B=1/10
2B=(1/10)-(1/50)
B=1/25
SO B COMPLETE THE TASK IN 25 DAYS

Suresh said:   1 decade ago
From given statement
A+B+C = 6/50 ( A+B = 1/10 and C = 1/50)

Substitute A= B+C in above equation to get A= 3/50
3/50+B+1/50 = 6/50

B = 1/25

25 days

Mohanapriyadarshini said:   1 decade ago
@awoke

How come 2 b's ?

A + B = 1/10 but A = B + C, then
A + B = B + B + C = 1/10 and C = 1/50

a value is a+b ,what about b+c, why you are adding b+b+c ?

Nikhil said:   1 decade ago
Mr.Awoke your method is awesome and moreover its applicable to all such type of probs...thanks!

Pavan@9966606261 said:   1 decade ago
A=B+C;
A+B=1/10;
A-B=1/50;
2A=1/10+1/50=6/50;
A=3/50;
A-B=1/50;
B=3/50-1/50;
B=1/25;
B ALONE CAN DO IN "25" DAYS

Sowmya said:   1 decade ago
@awoke.

Your method is awesome.

Rakesh sonowal said:   1 decade ago
A=B+C (1)
A+B 1 Day work=1/10 (2)
Cs 1 Day work=1/50 (3)
putin eq (1) n (3) in eq (2)
2B +1/50=1/10
2B=1/10-1/50
2B=(5-1)/50
2B=4/50
B=4/50 =1/25
So Bs 1 day work =1/25.
So B alone could do d work in 25 days.

GAURAV said:   1 decade ago
TIME FOR CERTAIN WORK....
A=B+C .....................................i
FOR
A+B=10 DAY.......SO(A+B)_1DAY WORK=1/10
.>A=1/10-B.......................ii
C=50 DAY.........1 DAY C WORK=1/50......................iii
SO ...FOR B=A-C.........................FROM i
B=1/10-B-1/50
2B=1/10-1/50
B=1/25
.........SO B REQUIRE 25 DAYS