44.
Which of the following operation is first performed?
Spot facing
Boring
Tapping
Drilling
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
40 comments Page 2 of 4.

Milind sardar said:   9 years ago
The correct is:

Drilling - Boring - Tapping - Spot facing.

Manvijay said:   9 years ago
It must be drilling first. Drilling is originating a hole and boring is enlarging the hole previously drilled in drilling.

Lokesh said:   9 years ago
Boring is the correct answer, because all other process are carried out after the drilling, so the sequence is drilling, boring, spot facing and tapping.

Pravin said:   9 years ago
How it is possible to bore first without drilling?

Jay said:   9 years ago
The answer must be drilling.

Ravi Gupta said:   9 years ago
The answer should be drilling.

Because boring & tapping definitely will not be correct. And spot facing used where free hole needed for properly for sitting the head of Allen key bolt.

P das said:   9 years ago
Drilling > Boring > Reaming > Tapping > Spot Facing.

Ashish patidar said:   9 years ago
Drilling is the correct answer. Also boring is enlarging existing hole and spot facing is done after threading and some how tapping.

Amiya Mishra said:   9 years ago
1:Drilling#manufacturing of a specific diameter hole.

2:Boring#enlarging of the existing hole.

3:Tapping#used for fine finishing of the internal surface of a hole.

4:Spot facing#smooting and squaring of the surface around a hole.

Hence drilling is the correct answer.

Ankush said:   9 years ago
Drilling should be first.