16.
Which of the following networks is correctly drawn?
Discussion:
23 comments Page 2 of 3.
Mohit said:
8 years ago
Option B is correct.
Because if you see the fig B clearly two arrows come from the same point so the two activities take place simultaneously. So, the end activity go to the last event and the diagram is completed.
Because if you see the fig B clearly two arrows come from the same point so the two activities take place simultaneously. So, the end activity go to the last event and the diagram is completed.
Urvashi said:
8 years ago
I think D is correct because no dangling.
Ghjudfe said:
1 decade ago
What is the difference between A and B?
Kaushal said:
9 years ago
None of the answers is correct D also not correct because dummy activity is used precedence relationship between 2 nodes.
Indrajeet said:
9 years ago
D is the correct answer.
Gajendrasinh rana said:
9 years ago
As per my knowledge, none of above answer is correct because no any activity occurs in a reverse manner as per project rule. So arrow not going towards down direction.
ANKIT CHAUDHARY said:
9 years ago
No yar. Answer [b] is right but in this question the fig of option [b] is wrong. Right figure indicates in are S KHURMI page number 744 question no.94 (figure of option [b] show).
Bhavesh Shingala said:
9 years ago
A & B both are same. So the answer is incorrect.
Rakesh said:
9 years ago
D is the correct answer. Because in option A, B and C a closed cycle is drawn which is not possible.
Mcdonald said:
10 years ago
How can B is correct?