6.
If the peak discharge of a storm water drain (S.W. Drain) is e.xpected to exceed 150 cumecs, the free board to be provided, is
100 cm
90 cm
80 cm
50 cm.
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
12 comments Page 2 of 2.

Lalit said:   6 years ago
Free board = ( 2/3 of peak discharge).
= ( 2/3 x 150 ).
= 100.
(5)

Mohammed said:   3 years ago
Thanks for explaining the answer.