26. 

Pick up the correct statement from the following :

A. Small sewers are cleaned by flushing
B. Medium sewers are cleaned by cane rodding
C. Medium sewers may be cleaned by pills
D. Large sewers are cleaned by removing the deposited materials
E. All the above.

Answer: Option E

Explanation:

No answer description available for this question. Let us discuss.

27. 

Cement concrete sewers are only suitable if non-scouring velocity is between

A. 2.5 to 3.0 m/sec
B. 3.0 to 4.0 m/sec
C. 3.5 to 4.5 m/sec
D. 4.5 to 5.5 m/sec.

Answer: Option A

Explanation:

No answer description available for this question. Let us discuss.

28. 

The grit chambers of sewage treatment plants, are generally cleaned after

A. 2 days
B. 5 days
C. 7 days
D. 12 days
E. 14 days.

Answer: Option E

Explanation:

No answer description available for this question. Let us discuss.

29. 

The spacing of bars for perforations in coarse screens used for the treatment of sewage, is

A. 20 mm
B. 30 mm
C. 40 mm
D. 50 mm
E. 100 mm.

Answer: Option D

Explanation:

No answer description available for this question. Let us discuss.

30. 

In very first stage of decomposition of the organic matter in sewage

A. nitrites are formed
B. nitrates are formed
C. carbondioxide is formed
D. ammonia is formed.

Answer: Option D

Explanation:

No answer description available for this question. Let us discuss.