Civil Engineering - UPSC Civil Service Exam Questions - Discussion
Discussion Forum : UPSC Civil Service Exam Questions - Section 1 (Q.No. 30)
30.
In a PERT network, the activity durations are given as to (optimistic), tp (pessimistic) and tm (most likely time). What is the variance of is activity ?
Discussion:
14 comments Page 2 of 2.
OMER said:
7 years ago
I think the correct Answer is C.
Sanathkumar said:
7 years ago
I think option C is the answer.
Rohit pal said:
6 years ago
Yes, the correct Answer is C.
Jainu said:
6 years ago
The right answer is C.
Option B is for the standard deviation.
Option A is for the expected time.
Option B is for the standard deviation.
Option A is for the expected time.