Civil Engineering - Surveying - Discussion

Discussion Forum : Surveying - Section 2 (Q.No. 12)
12.
For setting out a simple curve, using two theodolites.
offsets from tangents are required
offsets from chord produced are required
offsets from long chord are required
deflection angles from Rankine's formula are required
none of these.
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
11 comments Page 2 of 2.

Shubham said:   3 years ago
Answer E is correct.

Option A, B, C are linear methods of setting out a curve. And option D is an instrumental method but in Rankine's method of deflection angles, one theodolite and one tape are used to measure angle and length respectively.


Post your comments here:

Your comments will be displayed after verification.