Civil Engineering - Highway Engineering - Discussion
Discussion Forum : Highway Engineering - Section 2 (Q.No. 15)
15.
At a road junction, 7 cross conflict points are severe if
Discussion:
20 comments Page 2 of 2.
Shiv97 said:
6 years ago
Yes, If 1 one way and 1 two way conflict points will be 11. For both one way, it's 6 nearer to 7. Hence option 1 is correct.
Hardik said:
6 years ago
Both 2 way- crossing conflict 16 and merging conflicts 8 = 24.
One 2 way & other 1 way- crossing conflict 7 and merging conflict 4 = 11.
Both 1 way- crossing conflict 4 and merging conflicts 2 = 6.
One 2 way & other 1 way- crossing conflict 7 and merging conflict 4 = 11.
Both 1 way- crossing conflict 4 and merging conflicts 2 = 6.
(2)
Akshay said:
6 years ago
What is conflict?
Chetan d b said:
5 years ago
What is conflict point?
(1)
Ajay Sharma said:
5 years ago
Here...
A-2way
B-1 way..
Total conflict points =11,
Minor conflict points=4.
Cross conflict point=11 - 4 = 7.
A-2way
B-1 way..
Total conflict points =11,
Minor conflict points=4.
Cross conflict point=11 - 4 = 7.
Ashwani chaudhary said:
4 years ago
What is a conflict point?
(1)
Deepankar said:
4 years ago
Both roads one-way,Total conflicts=6;Major(also called Crossing)=4 and Minor (also called Merging) = 4.
One road one-way + other road two-way, Total conflicts =11;Major=7 and Minor= 4.
Both roads two-way,Total conflicts= 24;
Major=16,Minor=8.
One road one-way + other road two-way, Total conflicts =11;Major=7 and Minor= 4.
Both roads two-way,Total conflicts= 24;
Major=16,Minor=8.
(4)
Saqib Khattak said:
4 years ago
Thanks @Deepankar.
Paul said:
3 years ago
I think the right answer is D.
(1)
Aryan said:
2 years ago
In question keyword is severe, which means major.
Major conflict points are 7 in one 2-way and one 1-way road.
Major conflict points are 7 in one 2-way and one 1-way road.
(2)