Aptitude - Time and Work - Discussion

Discussion Forum : Time and Work - General Questions (Q.No. 9)
9.
A does 80% of a work in 20 days. He then calls in B and they together finish the remaining work in 3 days. How long B alone would take to do the whole work?
23 days
37 days
371/2
40 days
Answer: Option
Explanation:

Whole work is done by A in ( 20 x 5 ) = 25 days.
4

Now, ( 1 - 4 ) i.e., 1 work is done by A and B in 3 days.
5 5

Whole work will be done by A and B in (3 x 5) = 15 days.

A's 1 day's work = 1 , (A + B)'s 1 day's work = 1 .
25 15

Therefore B's 1 day's work = ( 1 - 1 ) = 4 = 2 .
15 25 150 75

So, B alone would do the work in 75 = 37 1 days.
2 2

Discussion:
164 comments Page 7 of 17.

Vishnu G said:   8 years ago
A alone completes the work in 25 days.
A and B together can complete the work in 15 days.
Let the total work be 75 units(LCM of 15 and 25).
i.e., A= 3 units /day ; A+B=5 units/day.
i.e.,B can do 2 units/day.
=> B alone can do the work in 75/2 days.

Sam said:   1 decade ago
Solution.

A's 1 day work = (80/100)*(1/20) = (1/25).

(A+B) 's 1 day work = (20/100)*(1/3) = (1/15).

So B's 1 day work will be (A+B) - (A).

B's 1 day work will be (2/75).

Hence 1 work will be completed by B alone in (75/2) days that's option C.

Seema duhan said:   1 decade ago
A = (1/20)*(80%) = (1/20)*(80/100) = 1/25. (EQUATION 1).

Remaining work=100%-80%=20%.

A+B=(1/3)*(20%)=(1/3)*(20/100)=1/15. (EQUATION 2).

Put equation 1 in equation 2, we get:
(1/25)+B = 1/15.
B = 2/75.

So B alone can do this work in 75/2 days.

Vineela said:   8 years ago
Let total work is 100.
A did 80 work in 20 days,
1day work =80/20 =4 (A's efficiency),
A+B did 20 work in 3 days,
1 day work = 20/3 (A+B's efficiency),
4+B = 20/3,
B=8/3 (b's efficiency),
B's did whole work i.e 100 in = 100*3/8 = 37 1/2 answer.

Supreeth said:   1 decade ago
St-1:

80%=20.

.'.(100*20)/80 = 25 days.

100%=?

St-2:

For 23 days A would have completed 23/25 part of the work,

St-3:

(25/25)-(23/25) = 2/25 part of work is completed by B in 3 days.

St-4:

.'. in 1 day (25/2)*3 = 37 1/2.

Win's said:   1 decade ago
80% work done by 20 day means 80/20 = 4% per day by A.

So 100/4 = 25 day for A.

He took B to do the remaining 20% task in three day.

Means A's contributions is 12% and B's 8% in three days.

So now B = 100/8*3 = 37.5 that's it.

Suganya said:   1 decade ago
Simple method:.

A's one day work 80/20=4%.

A's three days work 12%.

The remaining work is only done by B in that three days=20%-12%=8%.

B's one days work=8/3%.

B completes 100% work in.

8/3% * x =100%.

So x=75/2=37.5.

Karan said:   2 years ago
A = 80% in 20 days.
80% = 80/100 = 4/5.
A = 4% Daily work.

80-100 = 20% of work remaining.
20% of work done by A+B in 3 days.

A = 4% Daily work in 3 days.
A = 4×3=12%.
20 - 12 = 8%.
B = 8%.
B = 8/100%×3 = 37.5 = 37 1/2.
(95)

Rajendra said:   1 decade ago
A does 80% in 20 days..so
A does 100% in 25 days..
A's 1 day work=1/25
A+B does 20% in 3 days..so
A+B does 100% in 15 days
A+B's 1 day work=1/15
1/25+B=1/15
B=1/15-1/25
B,s 1 day work=2/75
so B,s work=75/2 i.e 37 1/2 days..
(2)

Ramya reddy said:   1 year ago
80% of the work in 20 days means 4/5.
100% he will complete in 25 days.
Now, the remaining 20% of the work in 3days means;
1-4/5 = 1/5 this is for one day
For 3days 3*1/5 = 1/15,
Now [1/15 - 1/25] = 2/75.
Rev= 75/2=37.5
(12)


Post your comments here:

Your comments will be displayed after verification.