Aptitude - Time and Work - Discussion
Discussion Forum : Time and Work - General Questions (Q.No. 9)
9.
A does 80% of a work in 20 days. He then calls in B and they together finish the remaining work in 3 days. How long B alone would take to do the whole work?
Answer: Option
Explanation:
Whole work is done by A in | ![]() |
20 x | 5 | ![]() |
= 25 days. |
4 |
Now, | ![]() |
1 - | 4 | ![]() |
i.e., | 1 | work is done by A and B in 3 days. |
5 | 5 |
Whole work will be done by A and B in (3 x 5) = 15 days.
A's 1 day's work = | 1 | , (A + B)'s 1 day's work = | 1 | . |
25 | 15 |
![]() |
![]() |
1 | - | 1 | ![]() |
= | 4 | = | 2 | . |
15 | 25 | 150 | 75 |
So, B alone would do the work in | 75 | = 37 | 1 | days. |
2 | 2 |
Discussion:
164 comments Page 13 of 17.
RAjesh Kumar said:
6 years ago
80% = 4/5.
A does 4/5 work in 20 days.
A 1 day work =(4/5)/20 = 1/25,
remaining work = 1/5.
A + B does 1/5 work in 3 days.
A + B 1 day work=(1/5)/3 = 1/15.
Therefore;
B's 1 day work = (a+b)-a = 1/15-1/25 = 2/75.
A does 4/5 work in 20 days.
A 1 day work =(4/5)/20 = 1/25,
remaining work = 1/5.
A + B does 1/5 work in 3 days.
A + B 1 day work=(1/5)/3 = 1/15.
Therefore;
B's 1 day work = (a+b)-a = 1/15-1/25 = 2/75.
Abica said:
5 years ago
Nice explanation, Thanks @Vikram Sihag.
Siddhant said:
5 years ago
80% work done by A -------->20 days (given)
1 work ie. 100% work done by A ------->20*100/80 = 25 days
therefore, total work is done by A = 25 days
Now,
20% work done by (A+B) implies,
20/100 work done --------> 3 days.
1 work ie. 100% work done in ------>3*100/20.= 15 days.
Now we have,
A's 1 days work = 1/25 ----------------------> 1
and, (A+B)'s 1 days work = 1/15 -------------------------> 2
Putting A's work in equation 2.
B's one day work = 2/75.
Therefrom total work done by B = 75/2.
= 37 1/2.
1 work ie. 100% work done by A ------->20*100/80 = 25 days
therefore, total work is done by A = 25 days
Now,
20% work done by (A+B) implies,
20/100 work done --------> 3 days.
1 work ie. 100% work done in ------>3*100/20.= 15 days.
Now we have,
A's 1 days work = 1/25 ----------------------> 1
and, (A+B)'s 1 days work = 1/15 -------------------------> 2
Putting A's work in equation 2.
B's one day work = 2/75.
Therefrom total work done by B = 75/2.
= 37 1/2.
Devika said:
5 years ago
Solution by LCM Method:
A does 80% of the work in 20 days => 4/5th of the work in 20 days
=> (4/5)x = 20 => x=25 days (No of days A takes to complete the work)
Remaining work = 1/5 which is completed by A+B in 3 days.
(1/5)x = 3 => x=15 days (No of days A+B takes to complete the work).
Therefore,
A - 25 days - 3 units.
A+B - 15 days - 5 units.
LCM - 75.
A+B = 5 => B=2 units.
Therefore, total work done by B = 75/2.
= 37 1/2.
A does 80% of the work in 20 days => 4/5th of the work in 20 days
=> (4/5)x = 20 => x=25 days (No of days A takes to complete the work)
Remaining work = 1/5 which is completed by A+B in 3 days.
(1/5)x = 3 => x=15 days (No of days A+B takes to complete the work).
Therefore,
A - 25 days - 3 units.
A+B - 15 days - 5 units.
LCM - 75.
A+B = 5 => B=2 units.
Therefore, total work done by B = 75/2.
= 37 1/2.
Surekha Merla said:
5 years ago
Let's take 5 parts total.
A finishes 80% of it in 20 days, A can finish whole work in 25 days.
A one day work is 1/25.
A= 4/5 work in 20 days.
Remaining, 1-(4/5)= 1/5 part.
(A+B)= 1/5 work in 3 days.
A's 3 days work = 3/25.
Therefore,
For 3 days, A+B= 1/5.
(3/25)+B= 1/5.
B= 2/25 in 3 days.
B's one day work, 2/75 work.
Whole work by B= 75/2.
B = 37 1/2 days.
A finishes 80% of it in 20 days, A can finish whole work in 25 days.
A one day work is 1/25.
A= 4/5 work in 20 days.
Remaining, 1-(4/5)= 1/5 part.
(A+B)= 1/5 work in 3 days.
A's 3 days work = 3/25.
Therefore,
For 3 days, A+B= 1/5.
(3/25)+B= 1/5.
B= 2/25 in 3 days.
B's one day work, 2/75 work.
Whole work by B= 75/2.
B = 37 1/2 days.
Sahil Negi said:
5 years ago
Thanks @Ganesh.
Mr pai said:
5 years ago
Thank you so much @Baskar.
Ravi said:
5 years ago
A do 80%work for 20days.
(Simplify it remaining 20%do in 5days).
Now work for 20%is 1/5 and work are done by both a+b is 1/3. Do lcm we get 15 and subtract 5-3/15=2/15.
Now it is 20% of work done by B is 2/15.
Now 20%*5=100% i.e,2/15*5=2/75 ans is 37 1/2 days.
(Simplify it remaining 20%do in 5days).
Now work for 20%is 1/5 and work are done by both a+b is 1/3. Do lcm we get 15 and subtract 5-3/15=2/15.
Now it is 20% of work done by B is 2/15.
Now 20%*5=100% i.e,2/15*5=2/75 ans is 37 1/2 days.
Pavani Durga said:
5 years ago
Thank you @Rajendra.
Rashmi said:
5 years ago
Thank you @Baskar.
Post your comments here:
Quick links
Quantitative Aptitude
Verbal (English)
Reasoning
Programming
Interview
Placement Papers