9.
A does 80% of a work in 20 days. He then calls in B and they together finish the remaining work in 3 days. How long B alone would take to do the whole work?
23 days
37 days
371/2
40 days
Answer: Option
Explanation:

Whole work is done by A in ( 20 x 5 ) = 25 days.
4

Now, ( 1 - 4 ) i.e., 1 work is done by A and B in 3 days.
5 5

Whole work will be done by A and B in (3 x 5) = 15 days.

A's 1 day's work = 1 , (A + B)'s 1 day's work = 1 .
25 15

Therefore B's 1 day's work = ( 1 - 1 ) = 4 = 2 .
15 25 150 75

So, B alone would do the work in 75 = 37 1 days.
2 2

Discussion:
164 comments Page 11 of 17.

SHIMEGHA.T.C said:   8 years ago
3(A+B)20%. = 80%(20A),
3/20*100. = 20/80*100A
15days(a+b). = 25 days A alone
B alone work = 1/25-1/15 = 2/75; 75/2.

Surya said:   8 years ago
How 1-4/5? Please explain it.

Gowtham said:   8 years ago
80/100 is 4/5 then how you get it as (20*5/4) =25?

Sweety said:   8 years ago
Thanks for the explanation @Baskar.

P srinivas Rao said:   8 years ago
A 80, of work = 80/100= 4/5 = 1/5.
A 100, of whole work = 100/80*20=25.
remaining work (A+B)= 1/5= 3days.
(A+B) total work= 3*5/1= 15 days.
B whole work= 25*15/10=37.5 answer.

Shree said:   8 years ago
Thanks for the explanation.

Vineela said:   7 years ago
Let total work is 100.
A did 80 work in 20 days,
1day work =80/20 =4 (A's efficiency),
A+B did 20 work in 3 days,
1 day work = 20/3 (A+B's efficiency),
4+B = 20/3,
B=8/3 (b's efficiency),
B's did whole work i.e 100 in = 100*3/8 = 37 1/2 answer.

Abhik said:   7 years ago
A 80% done in 20 days 100% done in 25 days.
Another A+B done 20%in 3 days 100% in 15 days.
Now B = 25*15/10=37.5.

Akil Prakash said:   7 years ago
Well said @mayuri.

Yash said:   7 years ago
We can solve it like this way also;

A do 80% of work in 20 days.

So,

A's one day's work = 80/100 * 1/20.
= 1/25.
Now A and B do remaining work in 3 days.
so we find remaining work and i.e. (1-1/25) = 24/25.
Now we multiply 24/25 by because of they(A and B) complete it in 3 days = 72/25 and the answer is 37 1/2.