Aptitude - Time and Work - Discussion

Discussion Forum : Time and Work - General Questions (Q.No. 9)
9.
A does 80% of a work in 20 days. He then calls in B and they together finish the remaining work in 3 days. How long B alone would take to do the whole work?
23 days
37 days
371/2
40 days
Answer: Option
Explanation:

Whole work is done by A in ( 20 x 5 ) = 25 days.
4

Now, ( 1 - 4 ) i.e., 1 work is done by A and B in 3 days.
5 5

Whole work will be done by A and B in (3 x 5) = 15 days.

A's 1 day's work = 1 , (A + B)'s 1 day's work = 1 .
25 15

Therefore B's 1 day's work = ( 1 - 1 ) = 4 = 2 .
15 25 150 75

So, B alone would do the work in 75 = 37 1 days.
2 2

Discussion:
164 comments Page 10 of 17.

Punitsw said:   10 years ago
In simple words:

A completes 80% in 20 days so would 92% in 23 days.

Remaining 8% completed by B in 3 days (21 - 23rd).

Now if B completes 8% in 3 days. So will be able to complete 100% in 37.5 days (3 x 100/8).

Inna said:   10 years ago
A's work 80% --- 20.

100% --- 25 (A).

A + B work (the remaining work means) 20% --- 3.

100% --- 15 (A+B).

(A+B) - A = B.

= 25*15/10 = 75/2 = 37*1/2.

Saravanan said:   10 years ago
Now I understand this concept.

Parvin Kumar said:   10 years ago
Hi all,

Work Completed = 80% = 80/100 = 4/5.

So, Remaining = 1- 4/5 = 1/5.

A + B complete this in 3 days so if they had continued total time required will be 5 * 3 = 15 days.

A individual complete it in 5/4 * 20 = 25 Days.
Then, B individual 1 day Work = 1/(A + B) - 1/A = 1/15 - 1/25 = 2/75.

So, B will complete whole work in 75/2 = 37 1/2.

Rahul said:   10 years ago
Hi, one easy and time-saving method is:

A done 80% work in 20 days.
So, one day work of A is = 80/20 = 4%.

Here, remaining work is = 100 - 80.
=20%.

A and B both together remaining work and they take 3 days to accomplish it.

During this three day, A's work is = 4% * 3 = 12%.
Then, B's work during 3 days = 8%.

Work - Days.
8% - 3.
100% - (?).

100 * 3/8 = 300/8 = 37.5 days.

Likhitha said:   10 years ago
A does 80% of work in 20 days.

Then A can do 100% of work in 25 days and 20% of work in 5 days.
A + B together finish the remaining 20% of work in 3 days.

For 20% of work B alone:
3/5 + 3/x = 1.
x = 7.5 days.

For 20% of work B alone takes 7.5 days then for 100% of work B takes,
20% = 7.5.
100% = ?.
100 * 7.5/20 = 37.5 = 37 1/2.

Rajkanya Saha said:   10 years ago
Too good @Baskar.

Thanks for explaining the answer.

Pooja Gowda said:   9 years ago
The total work is 100 unit.

A can do 80 unit in 20 days. So he can do 4 unit in 1 days.

Now A has finished 80 units so remaining work is 20 unit.

So, 20 unit work takes 3 days time to complete in which A will do 12 unit.
(since A do 4 unit/days).

Thus, B do 8 unit in 3 days.
And total work is 100 unit so B will take (3/8) * 100 = 37.5 days to complete total work.

Aakash Reddy said:   9 years ago
==>> A can do 80% W ---------> 20 days.

=> Then, 100% W ---------->

=> How many days(D), By Cross-multiplying we get,

D = (100*20)/80 ==> D = 25.

i.e., A can do 100% of the work in 25 days.

So, A's 1 day work, i.e., 1/A = 1/25 -----------------------(1)

The remaining work is 20%.

==>> Given A+B can do the 20% W --------> 3 days.

=> Then, 100% W ------------------------>

=> How many days(D), By cross-multiplying we get,

D = (100*3)/20 ==> D=15.

i.e., A+B can do 100% of work in 15 days.

So, A & B one day work i.e., 1/A + 1/B = 1/15 -----(2)

Solving 1 & 2, we get B's 1-day work as 1/B = 2/75.

So,

B alone would take to do the whole work i.e., B = 75/2 = 37(1/2) days.

Kriti said:   9 years ago
Hey guys 80/100 = 4/5 then why you people multiplying 5/4 * 20?


Post your comments here:

Your comments will be displayed after verification.