Aptitude - Time and Work - Discussion
Discussion Forum : Time and Work - General Questions (Q.No. 7)
7.
A can do a piece of work in 4 hours; B and C together can do it in 3 hours, while A and C together can do it in 2 hours. How long will B alone take to do it?
Answer: Option
Explanation:
A's 1 hour's work = | 1 | ; |
4 |
(B + C)'s 1 hour's work = | 1 | ; |
3 |
(A + C)'s 1 hour's work = | 1 | . |
2 |
(A + B + C)'s 1 hour's work = | ![]() |
1 | + | 1 | ![]() |
= | 7 | . |
4 | 3 | 12 |
B's 1 hour's work = | ![]() |
7 | - | 1 | ![]() |
= | 1 | . |
12 | 2 | 12 |
B alone will take 12 hours to do the work.
Discussion:
96 comments Page 7 of 10.
Himanshi mishra said:
8 years ago
@Ankita.
Follow this method.
Here total work is 12 hours as lcm of 2-4-3.
A does 3 work in 1 hour ND he finishes 12 work in four hours.
In the same way, abt A and C you know A does 3 work in 1 hour thus C also does 3 work in 1 hour so total work 6 in 1 hour thus 12 work in 2 hour is completed by A and C.
And now C does 3 work in 1 hour so b does 1 work in 1 hour and thus the both do 4 work in 1 hour and finishes in 3 hours.
As a result, B takes 1 hour to do 1 work so B Will take 12 hours to do 12 work.
Follow this method.
Here total work is 12 hours as lcm of 2-4-3.
A does 3 work in 1 hour ND he finishes 12 work in four hours.
In the same way, abt A and C you know A does 3 work in 1 hour thus C also does 3 work in 1 hour so total work 6 in 1 hour thus 12 work in 2 hour is completed by A and C.
And now C does 3 work in 1 hour so b does 1 work in 1 hour and thus the both do 4 work in 1 hour and finishes in 3 hours.
As a result, B takes 1 hour to do 1 work so B Will take 12 hours to do 12 work.
Sam said:
8 years ago
You explained well @Akshay.
Xyx said:
8 years ago
How it will 7/12-1/2=1/12?
(1)
Bunny said:
8 years ago
Thank you so much @Himanshi Mishra.
I was looking for this LCM method. This is way too easy. Thanks.
I was looking for this LCM method. This is way too easy. Thanks.
Rohit said:
8 years ago
Guys!.
I simply subtracted the (A's) work - (B's+C's)work
so I got,
1/4-1/3=-1/12 for 1hour.
hence for b to do alone his work 12 hour.
I simply subtracted the (A's) work - (B's+C's)work
so I got,
1/4-1/3=-1/12 for 1hour.
hence for b to do alone his work 12 hour.
Bits said:
8 years ago
A in 4hrs.
B+C _ 3.
A+C _ 2.
Total work by taking lcm of 4,3,2 is 12units.
A in one day do = 12/4= 3.
A+C_ 6.
So C=3.
In the same way,
B+C= 12/3 > 4.
So B=1.
At last B =12/1=12. That's the answer!.
B+C _ 3.
A+C _ 2.
Total work by taking lcm of 4,3,2 is 12units.
A in one day do = 12/4= 3.
A+C_ 6.
So C=3.
In the same way,
B+C= 12/3 > 4.
So B=1.
At last B =12/1=12. That's the answer!.
(1)
Shree said:
7 years ago
Clear and detailed explanation. Thank you all.
Akshay Ladwa said:
7 years ago
A=B+C(given) ----> (1)
one day work of A+B=1/10 --> (2)
one day work of C=1/50 ---> (3).
So for total (A+B+C)'s 1 day work, we can assume from 1--> C=A-B=1/50----> (4)
So adding equation 2 and 4 we get A=3/50.
Substituting above A in equation 2 we get B=1/25.
Hence 25 days because(If A's 1 day's work =1/n then A can finish the work in n days.)).
one day work of A+B=1/10 --> (2)
one day work of C=1/50 ---> (3).
So for total (A+B+C)'s 1 day work, we can assume from 1--> C=A-B=1/50----> (4)
So adding equation 2 and 4 we get A=3/50.
Substituting above A in equation 2 we get B=1/25.
Hence 25 days because(If A's 1 day's work =1/n then A can finish the work in n days.)).
Sukumar said:
7 years ago
Well said @Hindu.
Tejs said:
7 years ago
Thanks for your answer @Bits.
Post your comments here:
Quick links
Quantitative Aptitude
Verbal (English)
Reasoning
Programming
Interview
Placement Papers